Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
10/07/2021
Applicant:
Eli McVey
Description:
TI:RETAIL (AREA 1 & 4)

Permit Reviews

Permit Number - T21CM07976
Permit Status: Complete
Permit Description: TI:RETAIL (AREA 1 & 4)
Start Date Submittal Complete Date Status  
05/10/2022 REVISION - - 1ST 05/11/2022 COMPLETED Review Details
10/07/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 11/16/2021 COMPLETED Review Details
12/07/2021 RESUBMITTAL 12/21/2021 COMPLETED Review Details
01/03/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/04/2023 APPROVED Review Details

Conditions

Permit Number - T21CM07976
Permit Status: Complete
Permit Description: TI:RETAIL (AREA 1 & 4)
Date Description Comments
12/21/2021 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM07976
Permite Description: TI:RETAIL (AREA 1 & 4)
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
11/04/2022 COT - LCME - Mechanical Intermediate N/A Canceled Inspection Canceled
11/07/2022 COT - LCPL - Plumbing Final N/A Requested Inspection Canceled

Completed Inspections

Permit Status: Complete
Permit Number: T21CM07976
Permit Description: TI:RETAIL (AREA 1 & 4)
Total Completed Inspections - 23
Date Description Inspector Results Comments
03/15/2022 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 03/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 02/02/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Phase two.}
03/15/2022 COT - LCPL - Plumbing Above Ceiling Passed {Activity date: 03/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/15/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 03/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 02/02/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Phase two}
04/11/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/15/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
1. Support ceiling grid every 4 feet
2. Provide manufactures specs to support uni-strut and faux beams.
Proceed at risk.} ; {Activity date: 02/02/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Phase two. Soffit for phase one.}
04/11/2022 COT - LCBU - Framing Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Area 3.} ; {Activity date: 01/28/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval approval for area 1&2 ok to tside}
04/11/2022 COT - LCEL - Electrical Underground Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - PARTIAL APPROVAL FOR AREA 4 OK TO COVER
}
04/11/2022 COT - LCBU - Preslab Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - PARTIAL APPROVAL FOR AREA 4 OK TO PLACE CONCRETE

} ; {Activity date: 01/21/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready}
04/11/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/22/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA per text from contractor.} ; {Activity date: 01/28/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for area 1 ok to two side

}
04/11/2022 COT - LCPL - Rough Soil Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval for area 4 ok to cover
} ; {Activity date: 01/21/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for area 1 training room ok to cover
}
04/11/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 04/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/22/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA per text from contractor.} ; {Activity date: 02/15/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA phase four.

Sent text at 9:41

Before 2:00} ; {Activity date: 02/02/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Phase One}
04/15/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 04/15/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/17/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval for electrical LP13a ok for power

} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Area 3.} ; {Activity date: 01/28/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for areas 1&2 ok to 2side}
04/21/2022 COT - FCON - Alarm - Final Passed {Activity date: 04/21/2022; Status: Approved; Inspector: wmotto; Comment: Entered by CGATES1 - } ; {Activity date: 03/16/2022; Status: Partial Approval; Inspector: wmotto1; Comment: Entered by WMOTTO1 - 1. tested hornstrobes in area 1 everything passed in this area.}
04/21/2022 COT - FCON - Sprinkler - Final Passed {Activity date: 04/21/2022; Status: Approved; Inspector: wmotto; Comment: Entered by CGATES1 - } ; {Activity date: 03/16/2022; Status: Partial Approval; Inspector: wmotto1; Comment: Entered by WMOTTO1 - 1. Partial approval for area 1 of the remodle.}
04/21/2022 COT - FCON - Fire - Final Passed {Activity date: 04/21/2022; Status: Approved; Inspector: wmotto; Comment: Entered by CGATES1 - } ; {Activity date: 04/15/2022; Status: Denied; Inspector: JPEEL-DAVIS; Comment: Entered by JPEELDA1 - See permit T22FC00101 (Fire alarm) for notes. Fire alarm room shall have a sign that reads F.A.C.P. ROOM 3" Stroke red and white. Pay re-inspection fee's prior to calling back in the inspection.} ; {Activity date: 03/16/2022; Status: Partial Approval; Inspector: wmotto1; Comment: Entered by WMOTTO1 - 1. Ok to occupy area 1 per tucson fire. Ok for tco in area 1.}
12/30/2022 COT - LCBU - Building Final Passed
12/30/2022 COT - LCEL - Electrical Final Passed
12/30/2022 COT - LCME - Mechanical Final Passed
12/30/2022 COT - LCPL - Plumbing Final Passed
12/30/2022 COT - HCBU - Building Final Passed
12/30/2022 COT - HCEL - Electrical Final Passed
12/30/2022 COT - HCPL - Plumbing Final Passed
12/30/2022 COT - HCME - Mechanical Final Passed
01/13/2023 COT - LCEL - Outdoor Lighting Passed

Documents

File Name Document Type  
2022.03.15 TRAINING ROOM TCO_REQUEST_FORM_1-17-14FILLABLE.PDF DOCUMENTS VIEW
REV1_APPLICATION.PDF DOCUMENTS VIEW
REV1_ARCH_NARRATIVE.PDF DOCUMENTS VIEW
REV1_JOB CARD.PDF DOCUMENTS VIEW
REV1_PERMIT.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF DOCUMENTS VIEW
TCO.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
23A WATER REPORT-2022-12-18_V1.PDF DOCUMENTS VIEW
TARGET T1863 - TEST - BALANCE REPORT_V1.PDF DOCUMENTS VIEW
COMCHECK_MECH.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
CONTRACTOR - WT AZ ROC.PDF DOCUMENTS VIEW
COMPLIANCE-REPORT.PDF DOCUMENTS VIEW
PLBG PIPING SYS & EQUIP-US.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW