Permit: T21CM07858
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1355 W ROGER RD 12
Address NEW:
1355 W ROGER RD 12
Apply Date:
10/01/2021
Applicant:
Peter Meyer
Description:
Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Permit Reviews
Permit Number - T21CM07858
Permit Status: Complete
Permit Description: Remodel of 96 apartments located in 12 buildings plus remodel of community building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/01/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 12/23/2021 | COMPLETED |
| 12/15/2021 | RESUBMITTAL | 12/23/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM07858
Permit Status: Complete
Permit Description: Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 12/10/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 12/10/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
| 12/10/2021 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 12/10/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 12/10/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM07858
Permite Description: Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2022 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | corrections not completed. |
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 01/12/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
| 10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM07858
Permit Description: Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/11/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 04/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} ; {Activity date: 04/08/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR, cancelled by Contractor} | |
| 04/11/2022 | COT - LCBU - Framing | Passed | {Activity date: 04/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 04/11/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 04/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} ; {Activity date: 04/08/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR, cancelled by Contractor} | |
| 04/11/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 04/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap 4- A1 units and 4- C1 units in bldg 12 all ok to rock } ; {Activity date: 04/08/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR, cancelled by Contractor} |
|
| 08/15/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE RECN/ UNITS #12145, #12245, #12146, #12246, #12147, #12247, #12148, #12248 } |
|
| 08/15/2022 | COT - LCEL - Electrical Reconnect | Passed | {Activity date: 08/15/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved to reconnect (8) meter-pack for Bldg 12, please send RECN Clearance to TEP for units #12145, #12245, #12146, #12246, #12147, #12247, #12148, #12248} | |
| 11/07/2022 | COT - LCME - Mechanical Final | Passed | ||
| 12/01/2022 | COT - LCBU - Building Final | Passed | ||
| 12/01/2022 | COT - LCEL - Electrical Final | Passed | ||
| 12/09/2022 | COT - LCPL - Plumbing Final | Passed | ||
| 01/12/2023 | COT - LCBU - Building Progress | Passed | ||
| 01/12/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/12/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 01/12/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 01/12/2023 | COT - LCPL - Plumbing Above Ceiling | Passed |