Permit: T21CM07851
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1355 W ROGER RD BLDG 5
Address NEW:
1355 W ROGER RD BLDG 5
Apply Date:
10/01/2021
Applicant:
Peter Meyer
Description:
Bldg 5Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Permit Reviews
Permit Number - T21CM07851
Permit Status: Complete
Permit Description: Bldg 5Remodel of 96 apartments located in 12 buildings plus remodel of community building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/01/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 12/23/2021 | COMPLETED |
| 12/15/2021 | RESUBMITTAL | 12/23/2021 | COMPLETED |
Conditions
Permit Number - T21CM07851
Permit Status: Complete
Permit Description: Bldg 5Remodel of 96 apartments located in 12 buildings plus remodel of community building.
| Date | Description | Comments |
|---|---|---|
| 12/10/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM07851
Permite Description: Bldg 5Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/16/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Re-inspection required | 8/16/23: ABS not under test. Not ready for inspection. |
| 08/16/2023 | COT - LCPL - Plumbing Intermediate | N/A | Re-inspection required | 8/16/23: ABS not under test. Not ready for inspection. |
| 11/02/2023 | COT - LCEL - Electrical Reconnect | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM07851
Permit Description: Bldg 5Remodel of 96 apartments located in 12 buildings plus remodel of community building.
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/16/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 08/16/2023 | COT - LCBU - Framing | Passed | ||
| 08/16/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 08/16/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 08/16/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
| 08/18/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 08/18/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 10/25/2023 | COT - LCBU - Building Progress | Passed | ||
| 10/25/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 10/25/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 10/27/2023 | COT - LCEL - Electrical Final | Passed | ||
| 10/27/2023 | COT - LCBU - Building Final | Passed | ||
| 10/27/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 10/27/2023 | COT - LCME - Mechanical Final | Passed | ||
| 11/15/2023 | COT - LCPL - Gas Final | Passed |