Permit: T21CM07837
Permit Details
Apply Date:
09/30/2021
Applicant:
Ryan Repucci
Description:
Expansion of offices at existing mezzanine space.
Architects:
- Ryan Repucci
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T21CM07837
Permit Status: C of o
Permit Description: Expansion of offices at existing mezzanine space.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/30/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 11/09/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM07837
Permit Description: Expansion of offices at existing mezzanine space.
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2021 | PLUMBING - FINAL | DBENOIT | Approved | WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION |
| 11/09/2021 | MECHANICAL - FINAL | DBENOIT | Approved | AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION |
| 03/10/2022 | MECHANICAL - INTERMEDIATE | TLUNDBERG | Approved | AP |
| 03/10/2022 | PLUMBING - PRE SLAB | TLUNDBERG | Approved | AP |
| 03/10/2022 | FRAMING | TLUNDBERG | Approved | AP. Ok rock both sides |
| 03/17/2022 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Approved |
| 03/17/2022 | MODULAR - BUILDING INSPECTION | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | MOBILE HOME SITE LOC./SET-UP | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | PLUMBING - BACK WATER VALVE | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | ELECTRIC - UFER | DMUNIZ | Approved | Not Applicable. |
| 03/17/2022 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 03/17/2022 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 03/17/2022 | BUILDING - PROGRESS | DMUNIZ | Approved | Approved |
| 03/25/2022 | FIREWALL/FIREBARRIER/FIRESTOP | TGAUSP | Approved | Approved occupancy separation wall |
| 04/12/2022 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 04/12/2022 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 04/12/2022 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 04/29/2022 | FIRE SPKLR - FINAL | jfordney | Approved | |
| 04/29/2022 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
| 04/29/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | NA |
| 04/29/2022 | BUILDING - FINAL | TGAUSP | Approved | Approved, pending Fire |
| 05/25/2022 | FIRE - FINAL | jfordney | Approved |