Permit: T21CM07795
Permit Details
Apply Date:
09/29/2021
Applicant:
RAMON VALDEZ
Description:
NEW SFRS VALD000119 T19-M003
Permit Reviews
Permit Number - T21CM07795
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/29/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/11/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM07795
Permit Description: NEW SFRS VALD000119 T19-M003
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/12/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Ap |
| 10/13/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
| 10/13/2021 | ELECTRIC - UFER | DQUINN | Approved | Ap |
| 10/13/2021 | BUILDING PRE-SLAB | DQUINN | Approved | Ap |
| 10/18/2021 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | . Approved |
| 10/18/2021 | ROOF NAILING | ESTEVENS | Approved | . Approved |
| 10/21/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 10/21/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap Clear eco |
| 10/21/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
| 10/21/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Ap |
| 10/21/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | Ap |
| 10/21/2021 | FRAMING | DQUINN | Approved | Ap |
| 11/17/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 12/14/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | Ap Last 10’ of abs connected to septic tank - ok to backfill for COT. PCWW may want to see this as well. |
| 12/21/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 12/21/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 12/21/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 12/21/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 12/21/2021 | BUILDING - FINAL | DQUINN | Approved | Ap Close permit |
| 12/21/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | na |