Permit: T21CM07768
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
2701 E ARROYO CHICO
Address NEW:
2701 E ARROYO CHICO
Apply Date:
09/28/2021
Applicant:
Elliot Wnek
Description:
Sleeping Quarters & Porch
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM07768
Permite Description: Sleeping Quarters & Porch
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
| 10/26/2022 | COT - RSEL - Service Upgrade | N/A | Not Ready | |
| 10/27/2022 | RSME - Mechanical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Gas Pressure Test | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Masonry Pregrout | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM07768
Permit Description: Sleeping Quarters & Porch
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/01/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 03/01/2022 | COT - RSBU - Preslab | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 03/01/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/10/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, line installed and under test provide 1’ vertical clearance from new sewer main. Install tracer line.} ; {Activity date: 02/10/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
| 03/01/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 03/01/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/10/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, WASTE AND VENT under foundation installed and tested, install tracer line and call inspection for sewer connection. } ; {Activity date: 02/10/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} |
|
| 03/01/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 05/05/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 06/01/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 06/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 06/01/2022 | COT - LCBU - Framing | Passed | {Activity date: 06/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 11/10/2022 | COT - RSME - Mechanical Final | Passed | ||
| 11/10/2022 | RSBU - Building Final | Passed | ||
| 11/10/2022 | COT - RSPL - Plumbing Final | Passed | ||
| 11/10/2022 | COT - RSEL - Electrical Final | Passed |