Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Address NEW:
4940 E SCENIC PEAK WY
Apply Date:
09/07/2021
Applicant:
Russ Salmon
Description:
SFR LENNVC353 T20-M0033

Outstanding Activity Conditions

Permit Number - T21CM07200
Permit Status: Issued
Permit Description: SFR LENNVC353 T20-M0033
Total Outstanding Activity Conditions - 3
Date Name
09/07/2021 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
09/07/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
09/07/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Issued
Permit Number: T21CM07200
Permit Description: SFR LENNVC353 T20-M0033
Total Completed Inspections - 23
Date Description Inspector Results Comments
10/06/2021 COT - RSPL - Yard Water Line Passed {Activity date: 10/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
10/06/2021 COT - RSPL - Sewer Passed {Activity date: 10/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
10/06/2021 COT - RSPL - Rough Soil Passed {Activity date: 10/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
10/22/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 10/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
10/22/2021 COT - RSBU - Preslab Passed {Activity date: 10/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
10/22/2021 COT - RSEL - Electrical Underground Passed {Activity date: 10/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
10/22/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 10/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
12/01/2021 COT - RSBU - Roof Nailing Passed {Activity date: 12/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
12/01/2021 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 12/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
04/20/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO}
04/20/2022 COT - RSEL - Construction Power Passed {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP
TEP ECO

}
06/01/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 06/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/01/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 06/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/01/2022 RSME - Mechanical Progress Passed {Activity date: 06/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/20/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 06/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
08/16/2022 COT - BULD - SWG Clearance Passed {Activity date: 08/16/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - CODE GAS}
08/23/2022 COT - RSME - Mechanical Final Passed {Activity date: 08/23/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved}
08/23/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 08/23/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved 2090}
08/23/2022 COT - RSEL - Electrical Final Passed {Activity date: 08/23/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved}
08/24/2022 COT - LCBU - Framing Passed {Activity date: 08/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
08/24/2022 RSBU - Building Final Passed {Activity date: 08/24/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS
} ; {Activity date: 08/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Disposable need to be installed along with the tempered glass doors for master shower.
}
08/24/2022 COT - RSPL - Plumbing Final Passed {Activity date: 08/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Disposable need to be installed along with the tempered glass doors for master shower.} ; {Activity date: 08/16/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Clearance for southwest gas.} ; {Activity date: 08/15/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready. Install shut off valves. Have lines under pressure.}
08/24/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 08/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}