Permit Details

Status:
Issued
Type:
Commercial Building
Address:
533 N 4TH AV
Address NEW:
533 N 4TH AV
Apply Date:
09/03/2021
Applicant:
Vince Catalano
Description:
Replacing Existing Hood with New Hood and old equipment with new equipment

Permit Reviews

Permit Number - T21CM07165
Permit Status: Issued
Permit Description: Replacing Existing Hood with New Hood and old equipment with new equipment
Start Date Submittal Complete Date Status  
09/03/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/25/2021 COMPLETED Review Details
11/10/2021 RESUBMITTAL 11/22/2021 COMPLETED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM07165
Permite Description: Replacing Existing Hood with New Hood and old equipment with new equipment
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - ENGR - Site - Assurance Release N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T21CM07165
Permit Description: Replacing Existing Hood with New Hood and old equipment with new equipment
Total Completed Inspections - 14
Date Description Inspector Results Comments
04/18/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/18/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/18/2022 COT - LCBU - Framing Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/18/2022 COT - LCEL - Electrical Final Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/18/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
04/18/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 02/28/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Need completion and installation of hood.}
04/18/2022 COT - LCBU - Building Progress Passed {Activity date: 04/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved}
05/11/2022 COT - LCPL - Gas Pressure Test Passed {Activity date: 05/11/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved}
06/02/2022 COT - LCBU - Building Final Passed {Activity date: 06/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved pending Fire Finals.}
06/02/2022 COT - LCME - Mechanical Final Passed {Activity date: 06/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved}
06/02/2022 COT - LCME - Kitchen Hood Passed {Activity date: 06/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/28/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Duct system under smoke test. Ok to insulate and install duct system.}
06/02/2022 COT - FCON - Fire - Final Passed {Activity date: 06/02/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
06/02/2022 COT - FCON - Hood System - Final Passed {Activity date: 06/02/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
06/02/2022 COT - LCPL - Plumbing Final Passed {Activity date: 06/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved}