Permit Details

Status:
In Revision
Type:
Residential Building - One or Two Family
Address NEW:
4983 E BRIGHT WASH WY
Apply Date:
08/31/2021
Applicant:
Russ Salmon
Description:
SFR LENNVC353 T20-M0033

Outstanding Activity Conditions

Permit Number - T21CM07074
Permit Status: In revision
Permit Description: SFR LENNVC353 T20-M0033
Total Outstanding Activity Conditions - 3
Date Name
08/31/2021 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
08/31/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
08/31/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: In Revision
Permit Number: T21CM07074
Permit Description: SFR LENNVC353 T20-M0033
Total Completed Inspections - 23
Date Description Inspector Results Comments
10/05/2021 COT - RSPL - Yard Water Line Passed {Activity date: 10/05/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
10/05/2021 COT - RSPL - Sewer Passed {Activity date: 10/05/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
10/05/2021 COT - RSPL - Rough Soil Passed {Activity date: 10/05/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
10/14/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 10/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
10/14/2021 COT - RSBU - Preslab Passed {Activity date: 10/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
10/14/2021 COT - RSEL - Electrical Underground Passed {Activity date: 10/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
10/14/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 10/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
11/04/2021 COT - RSBU - Roof Nailing Passed {Activity date: 11/04/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - ) Approved} ; {Activity date: 11/04/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
11/05/2021 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 11/05/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - ) Approved} ; {Activity date: 11/04/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Fire block front entry, install H2.5 @ truss to top plate where missing, missing ANCHOR BOLTS, & Straps where needed.} ; {Activity date: 11/04/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, Fire block front entry, install H2.5 @ truss to top plate where missing, missing ANCHOR BOLTS, & Straps where needed.
}
03/30/2022 COT - LCBU - Framing Passed {Activity date: 03/30/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/24/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel all other inspections.} ; {Activity date: 03/17/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - }
03/30/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 03/30/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/24/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel all other inspections.} ; {Activity date: 03/17/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - }
03/31/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 03/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 03/30/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO
1. Support all 3”> ABS at 90’s
2. 3” ABS flat at ceiling in entry
3. Repair floor @ 2nd floor water closet
4. Support registers at 3 sides
5. Open AC chase at laundry
6. Maintain min 1” clearance around B-vent to combustibles
7. Line-set out of wall
8. C/O leaks at master bathroom shower} ; {Activity date: 03/24/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel all other inspections.} ; {Activity date: 03/17/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA
Cancel all other inspections}
03/31/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 03/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 03/30/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO} ; {Activity date: 03/24/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel all other inspections.} ; {Activity date: 03/17/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - }
03/31/2022 RSME - Mechanical Progress Passed {Activity date: 03/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 03/30/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO} ; {Activity date: 03/24/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel all other inspections.} ; {Activity date: 03/17/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - }
04/07/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 04/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
05/17/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO}
05/17/2022 COT - RSEL - Construction Power Passed {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP
TEP ECO} ; {Activity date: 05/12/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - NR}
06/09/2022 COT - BULD - SWG Clearance Passed {Activity date: 06/09/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE GAS}
07/20/2022 COT - RSME - Mechanical Final Passed {Activity date: 07/20/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
07/27/2022 RSBU - Building Final Passed {Activity date: 07/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/20/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CORRECTIONS REQUIRED , FIRE DOOR AT GARAGE NOT SELF LATCHING.}
07/27/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 07/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
07/27/2022 COT - RSPL - Plumbing Final Passed {Activity date: 07/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/20/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CORRECTIONS REQUIRED, 2ND FLOOR BATHROOM LAV TRAP ARM BACK-PITCHED.} ; {Activity date: 06/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, CLEAR SOUTHWEST GAS}
07/27/2022 COT - RSEL - Electrical Final Passed {Activity date: 07/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/20/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CORRECTIONS REQUIRED, 2ND FLOOR HALLWAY AND ATTIC RECEPTACLES HAVE OPEN GROUNDS.}