Permit: T21CM06955
Permit Details
Apply Date:
08/26/2021
Applicant:
RAMON VALDEZ
Description:
NEW SFRS VALD000119 T19-M003
Permit Reviews
Permit Number - T21CM06955
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/26/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 09/09/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM06955
Permit Status: Final
Permit Description: NEW SFRS VALD000119 T19-M003
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/26/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T21CM06955
Permit Description: NEW SFRS VALD000119 T19-M003
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/10/2021 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
| 09/10/2021 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Approved |
| 09/14/2021 | ELECTRIC - UFER | JBURGE | Approved | Approved . |
| 09/14/2021 | BUILDING PRE-SLAB | JBURGE | Approved | Approved . |
| 09/14/2021 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Approved Ok to place concrete in progress areas |
| 09/24/2021 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | Approved, okay to backfill |
| 10/04/2021 | ROOF NAILING | TGAUSP | Approved | Approved |
| 10/04/2021 | EXT METAL CLIPS/EXT SHEATHING | TGAUSP | Approved | Approved |
| 10/08/2021 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE ECO |
| 10/08/2021 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | Approved, please send ECO Clearance for construction power |
| 10/08/2021 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | Approved |
| 10/08/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | Approved |
| 10/08/2021 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved |
| 10/08/2021 | RESIDENTIAL INTERMEDIATE | TGAUSP | Approved | Approved |
| 10/08/2021 | FRAMING | TGAUSP | Approved | Approved |
| 11/22/2021 | BUILDING - FINAL | TGAUSP | Approved | Approved and complete |
| 11/22/2021 | ELECTRIC - FINAL | TGAUSP | Approved | - Approved |
| 11/22/2021 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | - Approved |
| 11/22/2021 | PLUMBING - FINAL | TGAUSP | Approved | - Approved |
| 11/22/2021 | MECHANICAL - FINAL | TGAUSP | Approved | - Approved |