Permit: T21CM06892
Permit Details
Apply Date:
08/24/2021
Applicant:
Description:
TI: CIRCLE K
Permit Reviews
Permit Number - T21CM06892
Permit Status: Issued
Permit Description: TI: CIRCLE K
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/23/2022 | REVISION - - 1ST | 06/08/2022 | COMPLETED |
| 08/24/2021 | COMMERCIAL - TI | 09/28/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM06892
Permite Description: TI: CIRCLE K
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
| 10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| 10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 10/26/2022 | COT - ENGR - Site - Assurance Release | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM06892
Permit Description: TI: CIRCLE K
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/06/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 07/06/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Conduits to new coffee brewing area. Ok to cover progress.} | |
| 07/06/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 07/06/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Waste line from new coffee location to main waste line. Ok to cover progress areas.} | |
| 07/13/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 07/13/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 07/13/2022 | COT - LCBU - Framing | Passed | {Activity date: 07/13/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to insulate and cover progress areas.} | |
| 09/26/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 09/26/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 09/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 09/26/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 10/12/2022 | COT - FCON - Alarm - Final | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - no fire alarm work was done} ; {Activity date: 09/02/2021; Status: Prior to Final Inspectn; Inspector: jvincent; Comment: Entered by JVINCEN1 - -Verify CO2 gas detection alarm, if applicable, and any modifications due to TI. Separate permits required for modifications/installation.} | |
| 10/12/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } |