Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM06738
Permit Details
Apply Date:
08/19/2021
Applicant:
Andrea Flood
Description:
SFR F40I19 T19-M0036
Completed Inspections
Permit Status: Complete
Permit Number: T21CM06738
Permit Description: SFR F40I19 T19-M0036
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/29/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 10/29/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/29/2021 | COT - RSPL - Sewer | Passed | {Activity date: 10/29/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/29/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/29/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
11/10/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 11/10/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
11/10/2021 | COT - RSBU - Preslab | Passed | {Activity date: 11/10/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
11/10/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 11/10/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
11/10/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 11/10/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
01/04/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
01/04/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
05/05/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - CODE ECO} | |
05/05/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved ok for clearance ECO } |
|
08/02/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/02/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/03/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/03/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/02/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE. Maintain min 1" clearance around B-vent to combustibles, maintain min slope on horizontal run} | |
08/16/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 08/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
10/10/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP SWG clearance required.} |
|
10/10/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
11/08/2022 | COT - RSME - Mechanical Final | Passed | ||
11/08/2022 | COT - RSEL - Outdoor Lighting | Passed | ||
11/16/2022 | COT - RSEL - Electrical Final | Passed | ||
11/16/2022 | RSBU - Building Final | Passed |