Permit: T21CM06724
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3100 N CAMPBELL AV #101*
Address NEW:
3100 N CAMPBELL AV #101*
Apply Date:
08/18/2021
Applicant:
EGLIN + BRESLER ARCHITECTS
Description:
REMAINING 5307SF -MINOR PATCHING AND REPAIRING, ADDING DOOR AND DEMISING WALL AND CREATING 697 S.F. COMMON AREA
Contractors:
- DPR CONSTRUCTION
Permit Reviews
Permit Number - T21CM06724
Permit Status: C of o
Permit Description: REMAINING 5307SF -MINOR PATCHING AND REPAIRING, ADDING DOOR AND DEMISING WALL AND CREATING 697 S.F. COMMON AREA
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/23/2021 | COMMERCIAL - TI | 10/20/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM06724
Permit Status: C of o
Permit Description: REMAINING 5307SF -MINOR PATCHING AND REPAIRING, ADDING DOOR AND DEMISING WALL AND CREATING 697 S.F. COMMON AREA
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/18/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM06724
Permit Description: REMAINING 5307SF -MINOR PATCHING AND REPAIRING, ADDING DOOR AND DEMISING WALL AND CREATING 697 S.F. COMMON AREA
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2021 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 12/01/2021 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | Pa Demising wall double 5/8X ok to tape. Above hallway lid area still to be done. |
| 12/01/2021 | FRAMING | DQUINN | Approved | Ap |
| 12/22/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap Ok to drop tiles |
| 12/22/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 02/02/2022 | FIRE - FINAL | MRoss | Approved | -Men's restroom EM light appears to not have power |
| 02/02/2022 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 04/08/2022 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
| 04/08/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |
| 04/08/2022 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | Ap Ok for C of O Close permit |
| 04/08/2022 | ENGINEERING - FINAL | DROBERTS | Approved | FINAL IS APPROVED |