Permit: T21CM06697
Permit Details
Apply Date:
08/17/2021
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
SFR KBME1609 T21-M0008
Contractors:
- KB HOME OF TUCSON *APA*
Outstanding Activity Conditions
Permit Number - T21CM06697
Permit Status: Final
Permit Description: SFR KBME1609 T21-M0008
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/17/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T21CM06697
Permit Description: SFR KBME1609 T21-M0008
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/17/2021 | PLUMBING - FINAL | GS | Approved | Wastewater receipt required P2F |
| 09/13/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Ap |
| 09/13/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 09/13/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | Ap |
| 09/22/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ap |
| 09/22/2021 | ELECTRIC - UFER | DQUINN | Approved | Ap |
| 09/22/2021 | BUILDING PRE-SLAB | DQUINN | Approved | Ap |
| 09/22/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
| 12/07/2021 | ROOF NAILING | ESTEVENS | Approved | Approved |
| 12/07/2021 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Approved |
| 02/24/2022 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | na |
| 02/24/2022 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap Remount outlets at kitchen counter and laundry room before rock. |
| 02/24/2022 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap |
| 02/24/2022 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
| 02/24/2022 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
| 02/24/2022 | FRAMING | DQUINN | Approved | Ap |
| 02/25/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 05/19/2022 | GAS CLEARANCE | DQUINN | Approved | CODE GAS |
| 05/26/2022 | BUILDING - FINAL | ESTEVENS | Approved | Approved |
| 05/26/2022 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | 1090.Approved |
| 05/26/2022 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved |
| 05/26/2022 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | Approved |
| 05/26/2022 | MECHANICAL - FINAL | ESTEVENS | Approved | Approved |