Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM06625
Permit Details
Apply Date:
08/16/2021
Applicant:
Lisa Bowers
Description:
TI: Restaurant and move Dumpster Location
Permit Reviews
Permit Number - T21CM06625
Permit Status: Complete
Permit Description: TI: Restaurant and move Dumpster Location
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/24/2022 | RESUBMITTAL | 02/15/2022 | COMPLETED |
06/02/2022 | REVISION - - 1ST | 06/13/2022 | COMPLETED |
08/16/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/15/2021 | COMPLETED |
03/27/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/04/2023 | APPROVED |
04/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/11/2023 | APPROVED |
Conditions
Permit Number - T21CM06625
Permit Status: Complete
Permit Description: TI: Restaurant and move Dumpster Location
Date | Description | Comments |
---|---|---|
04/04/2023 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM06625
Permite Description: TI: Restaurant and move Dumpster Location
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2022 | COT - LCEL - Grounding/Bonding | N/A | Canceled | {Activity date: 10/11/2022; Status: Not Applicable; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Not applicable} |
10/19/2022 | COT - LCEL - Construction Power | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NA} |
10/19/2022 | COT - LCEL - Temporary Service | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NA} |
10/19/2022 | COT - LCEL - Service Upgrade | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NA} |
02/02/2023 | COT - LCBU - Building Above Ceiling | N/A | Not Applicable | above ceiling already inspected and approved |
07/14/2023 | PDSD Building Division Pre-Construction Meeting | N/A | Canceled |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM06625
Permit Description: TI: Restaurant and move Dumpster Location
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/08/2022 | COT - LCPL - Sewer | Passed | {Activity date: 07/08/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
09/12/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
09/12/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
09/12/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
09/12/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 09/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
09/19/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} | |
10/19/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
10/19/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
12/16/2022 | COT - LCEL - Electrical Reconnect | Passed | ||
12/16/2022 | COT - LCBU - Preslab | Passed | ||
12/16/2022 | COT - LCPL - Gas Reconnect | Passed | ||
12/16/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/16/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
12/16/2022 | COT - LCPL - Gas Pressure Test | Passed | ||
04/05/2023 | COT - LCME - Kitchen Hood | Passed | ||
04/05/2023 | COT - LCME - Mechanical Final | Passed | ||
04/05/2023 | COT - LCBU - Building Final | Passed | ||
04/05/2023 | COT - FCON - Hood System - Final | Passed | ||
04/05/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
04/05/2023 | COT - LCEL - Electrical Final | Passed | ||
04/05/2023 | COT - LCPL - Plumbing Final | Passed | ||
04/05/2023 | COT - LCME - Mechanical Progress | Passed | ||
04/05/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
04/05/2023 | COT - LCEL - Electrical Progress | Passed | ||
04/05/2023 | COT - FCON - Fire - Final | Passed | ||
04/05/2023 | COT - LCPL - Plumbing Progress | Passed | ||
04/05/2023 | COT - FCON - Alarm - Final | Passed | ||
04/05/2023 | BULD - Electrical Clearance | Passed | ||
04/05/2023 | COT - BULD - SWG Clearance | Passed |