Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM06603
Permit Details
Apply Date:
08/13/2021
Applicant:
Mark Abel Architects P.C.
Description:
RESTAURANT
Architects:
- Mark Abel Architects PC
Contractors:
- MCMANUS CONSTRUCTION LLC
Permit Reviews
Permit Number - T21CM06603
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/13/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/14/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM06603
Permit Description: RESTAURANT
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/24/2021 | MECHANICAL - FINAL | DBENOIT | Approved | AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION |
11/30/2021 | FRAMING | RCHANDLER | Approved | -AP |
11/30/2021 | BUILDING ABOVE CEILING | RCHANDLER | Approved | -AP |
11/30/2021 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | -AP |
11/30/2021 | MECHANICAL - PROGRESS | RCHANDLER | Approved | -AP. Lobby and bathrooms Rough in. |
12/01/2021 | ELECTRIC - ABOVE CEILING | TLUNDBERG | Approved | PA All rough electric above new framing in hall and counter area approved. |
12/02/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | cancelled by Contractor |
12/03/2021 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | AP |
12/10/2021 | ELECTRIC - PROGRESS | RCHANDLER | Approved | CA per contractor. |
12/10/2021 | BUILDING - PROGRESS | RCHANDLER | Approved | AP tower pop- outs two and three. |
12/10/2021 | SHEET ROCK NAILING | RCHANDLER | Approved | AP |
12/14/2021 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Partial approval for two columns see building progress for third at drywall |
12/30/2021 | STUCCO MESH | WGALLAGHER | Approved | Partial approval for the West side, 1/2 of the north side, and 1/2 of the south side of the building ok to stucco |
01/27/2022 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Approved |
01/27/2022 | PLUMBING - PROGRESS | WGALLAGHER | Approved | Approved |
02/07/2022 | PLUMBING - FINAL | ESTEVENS | Approved | Approved |
02/07/2022 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | Approved |
02/15/2022 | FIRE - FINAL | MRoss | Approved | -Operational permits needed for Places of Assembly and CO2 gasses through the Tucson Fire Department. |
04/14/2022 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | AP |
04/14/2022 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | AP |
04/19/2022 | ELECTRIC - FINAL | RCHANDLER | Approved | AP |
08/17/2022 | BUILDING - FINAL | ESTEVENS | Approved |