Permit: T21CM06494
Permit Details
Apply Date:
08/10/2021
Applicant:
Brandy Burke
Description:
Construction of a new automated car wash
Permit Reviews
Permit Number - T21CM06494
Permit Status: Complete
Permit Description: Construction of a new automated car wash
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/10/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/15/2021 | COMPLETED |
| 11/01/2021 | RESUBMITTAL | 12/13/2021 | COMPLETED |
| 12/20/2021 | RESUBMITTAL | 02/08/2022 | COMPLETED |
| 03/13/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/14/2023 | APPROVED |
| 02/16/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/01/2023 | APPROVED |
Conditions
Permit Number - T21CM06494
Permit Status: Complete
Permit Description: Construction of a new automated car wash
| Date | Description | Comments |
|---|---|---|
| 12/23/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 12/23/2021 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 12/23/2021 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 12/23/2021 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 12/23/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 12/23/2021 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 12/23/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM06494
Permite Description: Construction of a new automated car wash
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 12/08/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 02/22/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | N/A |
| 03/06/2023 | COT - LCPL - Backwater Valve | N/A | Deferred | |
| 03/08/2023 | COT - LCBU - Building Final | N/A | Partial Pass |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM06494
Permit Description: Construction of a new automated car wash
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 06/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 07/08/2022 | COT - LCBU - Preslab | Passed | {Activity date: 07/08/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 08/24/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved. Stem wall and column finals.} ; {Activity date: 07/28/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, EXTERIOR column footings and piers for Entry canopy ok for concrete placement.} ; {Activity date: 06/28/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for building stem wall up to bottom of floor } ; {Activity date: 06/27/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA per call from contractor.} ; {Activity date: 06/24/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA per voicemail from contractor. } ; {Activity date: 06/15/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Building footprint.} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Stemwall for trough.} ; {Activity date: 05/12/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second pour of trench.} ; {Activity date: 04/26/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - } |
|
| 08/24/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 09/15/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/05/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval for towers only } |
|
| 09/23/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 09/23/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/05/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval awaiting special inspections } |
|
| 09/23/2022 | COT - LCPL - Plumbing Roof Drains | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 09/23/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 09/23/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/13/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/13/2022 | COT - HCBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/13/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 11/17/2022 | COT - LCPL - Rough Soil | Passed | ||
| 11/18/2022 | COT - LCPL - Sewer | Passed | ||
| 11/17/2022 | COT - LCEL - Electrical Underground | Passed | ||
| 12/02/2022 | COT - LCEL - Electrical Progress | Passed | UG conduits to pay stations. | |
| 12/29/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
| 12/29/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 12/29/2022 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 12/29/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 02/22/2023 | COT - LCME - Mechanical Final | Passed | ||
| 02/22/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 03/02/2023 | COT - LCBU - Sustainability | Passed | ||
| 03/02/2023 | COT - LCEL - Service Upgrade | Passed | ||
| 03/06/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 03/06/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 03/06/2023 | COT - FCON - Fire - Final | Passed | ||
| 03/08/2023 | COT - LCEL - Electrical Final | Passed | ||
| 03/16/2023 | COT - LCBU - Building Final | Passed | type panel schedule, toilet flush handle not on door side 3-8-23: OK for TCO Level Two. Reschedule when site is passed. March 16th: Ok to issue Certificate of Occupancy. |