Permit: T21CM06355
Permit Details
Status:
Expired
Type:
Commercial Building
Address:
6872 E TANQUE VERDE RD
Address NEW:
6872 E TANQUE VERDE RD
Apply Date:
08/05/2021
Applicant:
Description:
Tenant improvement for a new doughnut shop. Work will include replacing existing lighting and provid
Permit Reviews
Permit Number - T21CM06355
Permit Status: Expired
Permit Description: Tenant improvement for a new doughnut shop. Work will include replacing existing lighting and provid
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/05/2021 | COMMERCIAL - TI | 08/26/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Expired
Permit Number: T21CM06355
Permite Description: Tenant improvement for a new doughnut shop. Work will include replacing existing lighting and provid
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2021 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 10/19/2021; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - NA} |
| 10/19/2021 | COT - LCPL - Rough Soil | N/A | Canceled | {Activity date: 10/19/2021; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - NA} |
| 11/04/2022 | COT - ENGR - Site - Assurance Release | N/A | Canceled | Inspection Canceled |
| 11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
| 11/07/2022 | COT - LCBU - CofO | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM06355
Permit Description: Tenant improvement for a new doughnut shop. Work will include replacing existing lighting and provid
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2021 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 10/19/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/19/2021 | COT - LCBU - Framing | Passed | {Activity date: 10/19/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/19/2021 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/19/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 11/09/2021 | COT - LCPL - Gas Pressure Test | Passed | {Activity date: 11/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP. SWG clearance.} ; {Activity date: 10/19/2021; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - NR} | |
| 12/23/2021 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 10/19/2021; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - NR} | |
| 12/23/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 12/23/2021 | COT - FCON - Fire - Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } | |
| 12/23/2021 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 12/23/2021 | COT - LCBU - Building Progress | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 12/23/2021 | COT - FCON - Hood System - Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - 1. The kitchen hood has been servced and is up to date.} | |
| 12/23/2021 | COT - LCPL - Plumbing Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 01/06/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 01/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE GAS} ; {Activity date: 11/09/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE GAS} | |
| 02/01/2022 | COT - LCME - Mechanical Final | Passed | {Activity date: 02/01/2022; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 01/06/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. SWG clearance only.} ; {Activity date: 12/23/2021; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Pending balance report approval.} ; {Activity date: 08/18/2021; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - AIR BALANCE REPORT REQUIRED} |