Permit: T21CM06267
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2222 E BLACKLIDGE DR
Address NEW:
2222 E BLACKLIDGE DR
Apply Date:
08/02/2021
Applicant:
Donald Livingstone
Description:
Convert Garage to Sleeping Quarters
Permit Reviews
Permit Number - T21CM06267
Permit Status: Complete
Permit Description: Convert Garage to Sleeping Quarters
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/06/2022 | RESUBMITTAL | 06/29/2022 | COMPLETED |
| 08/02/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/11/2022 | COMPLETED |
| 09/22/2022 | RESUBMITTAL | 09/22/2022 | COMPLETED |
| 10/06/2022 | RESUBMITTAL | 10/11/2022 | COMPLETED |
Conditions
Permit Number - T21CM06267
Permit Status: Complete
Permit Description: Convert Garage to Sleeping Quarters
| Date | Description | Comments |
|---|---|---|
| 10/11/2022 | General Contractor Letter (GCL) or Owner/Builder Waiver required prior to permit issuance |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM06267
Permite Description: Convert Garage to Sleeping Quarters
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/09/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 05/09/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 10/26/2022 | COT - RSEL - Electrical Underground | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Rough Soil | N/A | Not Ready | |
| 12/21/2022 | COT - LCBU - Framing | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM06267
Permit Description: Convert Garage to Sleeping Quarters
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/09/2022 | COT - RSPL - Rough Soil | Passed | ||
| 12/09/2022 | COT - RSPL - Yard Water Line | Passed | ||
| 02/22/2023 | RSME - Mechanical Progress | Passed | ||
| 02/22/2023 | RSEL - Electrical Progress | Passed | ||
| 02/22/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
| 03/10/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 03/10/2023 | RSPL - Plumbing Progress | Passed | ||
| 03/17/2023 | COT - LCBU - Framing | Passed | Framing match plans onsite. Okay to insulate and sheet rock walls and ceiling. | |
| 07/13/2023 | COT - RSME - Mechanical Final | Passed | ||
| 07/13/2023 | RSBU - Building Final | Passed | ||
| 07/13/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/13/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 07/13/2023 | COT - RSEL - Electrical Final | Passed |