Permit: T21CM06241
Permit Details
Apply Date:
08/02/2021
Applicant:
Color Room Design LLC
Description:
Workshop
Contractors:
- Global Construction
Permit Reviews
Permit Number - T21CM06241
Permit Status: Final
Permit Description: Workshop
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/02/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/30/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM06241
Permit Description: Workshop
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2021 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | Approved |
| 10/07/2021 | BUILDING PRE-SLAB | WGALLAGHER | Approved | Approved |
| 10/07/2021 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | Approved |
| 10/07/2021 | EXCAVATION/LAYOUT REBAR & ZON | IVR USER | Approved | IVRS - RI canceled |
| 11/02/2021 | ROOF NAILING | WGALLAGHER | Approved | Approved |
| 11/02/2021 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Approved |
| 11/23/2021 | FRAMING | TGAUSP | Approved | Approved |
| 11/23/2021 | RESIDENTIAL INTERMEDIATE | TGAUSP | Approved | Approved |
| 11/23/2021 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | Approved |
| 12/10/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
| 12/10/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 12/10/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 03/23/2022 | MECHANICAL - FINAL | ESTEVENS | Approved | Approved |
| 03/23/2022 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved |
| 03/23/2022 | BUILDING - FINAL | ESTEVENS | Approved | Approved |