Permit: T21CM06207
Permit Details
Apply Date:
07/30/2021
Applicant:
Andrea Flood
Description:
SFR F40J19 T19-M0035
Outstanding Activity Conditions
Permit Number - T21CM06207
Permit Status: Issued
Permit Description: SFR F40J19 T19-M0035
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/30/2021 | SWR_SAGUARO TRAILS SQ20172860622 NWLY PTN BLOCK 6SAGUARO TRAILS - BLOCK 6 - PHASE 1 - LOT 155 - BACKWATER VALVE REQUIRED - ISSUED WITH $1,100.00 CONNECTION FEE DISCOUNT (CFD) PER SEWER SERVICE AGREEMENT AND PER PCRWRD/FRANCISCO GALINDO'S EMAIL DATED 6/2/21 - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM06207
Permit Description: SFR F40J19 T19-M0035
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/29/2021 | COT - RSPL - Sewer | Passed | {Activity date: 09/29/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
09/29/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/29/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/06/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/06/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/06/2021 | COT - RSBU - Preslab | Passed | {Activity date: 10/06/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/06/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 10/06/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/06/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/06/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
02/14/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 12/13/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
02/14/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 02/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
02/14/2022 | COT - LCBU - Framing | Passed | {Activity date: 02/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
02/14/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 02/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 02/09/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready see previous discrepancy } ; {Activity date: 12/13/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval missing 2 hold downs on rear patio} |
|
02/14/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 02/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
02/16/2022 | RSME - Mechanical Progress | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: TLUNDBURG; Comment: Entered by RSALDAT1 - 1080} | |
04/11/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 04/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO} | |
04/11/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 04/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP TEP ECO} |
|
04/12/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
05/19/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 05/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
05/24/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } | |
05/25/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/25/2022 | RSBU - Building Final | Passed | {Activity date: 05/25/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 05/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/25/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/29/2021; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. No text at this time; bury at own risk.} | |
05/25/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/25/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/19/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA SWG clearance required} ; {Activity date: 07/30/2021; Status: Prior to Final Inspectn; Inspector: CVASQUE2; Comment: Entered by CVASQUE2 - SWR_SAGUARO TRAILS SQ20172860622 NWLY PTN BLOCK 6 SAGUARO TRAILS - BLOCK 6 - PHASE 1 - LOT 155 - BACKWATER VALVE REQUIRED - ISSUED WITH $1,100.00 CONNECTION FEE DISCOUNT (CFD) PER SEWER SERVICE AGREEMENT AND PER PCRWRD/FRANCISCO GALINDO'S EMAIL DATED 6/2/21 - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD} |
|
05/25/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} |