Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
07/26/2021
Applicant:
Russ Salmon
Description:
SFR LENNVC353 T20-M0033

Outstanding Activity Conditions

Permit Number - T21CM06055
Permit Status: Issued
Permit Description: SFR LENNVC353 T20-M0033
Total Outstanding Activity Conditions - 1
Date Name
07/26/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Conditions

Permit Number - T21CM06055
Permit Status: Issued
Permit Description: SFR LENNVC353 T20-M0033
Date Description Comments
07/26/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)

Completed Inspections

Permit Status: Issued
Permit Number: T21CM06055
Permit Description: SFR LENNVC353 T20-M0033
Total Completed Inspections - 23
Date Description Inspector Results Comments
09/23/2021 COT - RSPL - Yard Water Line Passed {Activity date: 09/23/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/23/2021 COT - RSPL - Sewer Passed {Activity date: 09/23/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/23/2021 COT - RSPL - Rough Soil Passed {Activity date: 09/23/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
10/12/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 10/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
10/12/2021 COT - RSBU - Preslab Passed {Activity date: 10/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
10/12/2021 COT - RSEL - Electrical Underground Passed {Activity date: 10/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
10/12/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 10/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
11/04/2021 COT - RSBU - Roof Nailing Passed {Activity date: 11/04/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/28/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready}
11/04/2021 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 11/04/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/28/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready}
03/24/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/21/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR
Corrections have not been started. Cancel all other inspections.} ; {Activity date: 03/17/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CO
1. Fill holes in garage ceiling and wall
2. Flush blocking to framing at sear walls
3. Support 3” ABS at 90’s
4. Support sagging ABS in garage ceiling
5. Replace water soaked 12” duct in garage and in 2nd floor chase
6. Attach flange to floor
7. Nail plate ABS at stair landing
8. Block base of stair landing
9. Sister new stud to over-notched stud behind 2nd floor tub
10. Clean outs missing at 2nd floor tub and at shower per plan
11. Install shower floor and water test
12. Straighten blocking at master bath vanity
13. Air test solar copper lines in garage and nail plate lines in master closet
14. Move vent 10 feet from fresh air intake

OK to stucco}
03/24/2022 COT - LCBU - Framing Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/17/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA}
03/24/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/17/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CO}
03/24/2022 RSME - Mechanical Progress Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/17/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CO}
03/24/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
04/04/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 04/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
05/27/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 05/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO}
05/27/2022 COT - RSEL - Construction Power Passed {Activity date: 05/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP
TEP ECO} ; {Activity date: 05/12/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - NR}
06/09/2022 COT - BULD - SWG Clearance Passed {Activity date: 06/09/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE GAS}
06/27/2022 COT - RSME - Mechanical Final Passed {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/27/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/27/2022 COT - RSPL - Plumbing Final Passed {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, clear Southwest Gas}
06/27/2022 COT - RSEL - Electrical Final Passed {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
07/11/2022 RSBU - Building Final Passed {Activity date: 07/11/2022; Status: Approved; Inspector: KEN; Comment: Entered by KKARSEN1 - CERT FILED} ; {Activity date: 06/27/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS
}

Documents

File Name Document Type  
SIC.PDF DOCUMENTS VIEW
TRUSS CALC.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
SITE PLAN.PDF CONSTRPLANS VIEW