Permit: T21CM06045
Permit Details
Apply Date:
07/26/2021
Applicant:
Description:
SFR LENNVC451 T20-M0031
Outstanding Activity Conditions
Permit Number - T21CM06045
Permit Status: Expired
Permit Description: SFR LENNVC451 T20-M0031
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
07/26/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
07/26/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM06045
Permit Description: SFR LENNVC451 T20-M0031
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
09/14/2021 | COT - RSPL - Sewer | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
09/14/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/13/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
09/22/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/22/2021 | COT - RSBU - Preslab | Passed | {Activity date: 09/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/22/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
09/22/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
10/20/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/20/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready, provide ladder for further inspection. } |
|
10/20/2021 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/20/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/18/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - partial, install clips at 4 point bearing truss where missed, seal column chase at garage entry. Finish QA corrections prior to inspection.} | |
01/19/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
01/19/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
01/19/2022 | RSME - Mechanical Progress | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
01/19/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
01/31/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 01/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
02/02/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/02/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO} | |
02/02/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 02/02/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved Clear TEP ECO} | |
03/21/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 03/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
04/14/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/14/2022 | COT - LCBU - Framing | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved 1090} | |
04/14/2022 | RSBU - Building Final | Passed | {Activity date: 04/14/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/14/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved 2090} | |
04/14/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/21/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA SWG clearance required.} |
|
04/14/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} |