Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
07/26/2021
Applicant:
Andrea Flood
Description:
SFR STF40K T20-M0039

Outstanding Activity Conditions

Permit Number - T21CM06027
Permit Status: Issued
Permit Description: SFR STF40K T20-M0039
Total Outstanding Activity Conditions - 3
Date Name
07/26/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
07/26/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/26/2021 SWR_SAGUARO TRAILS SQ20172860622 NWLY PTN BLOCK 6SAGUARO TRAILS - BLOCK 6 - PHASE 1 - LOT 149 - ISSUED WITH $1,100.00 CONNECTION FEE DISCOUNT (CFD) PER SEWER SERVICE AGREEMENT AND PER PCRWRD/FRANCISCO GALINDO'S EMAIL DATED 6/2/21 - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD

Completed Inspections

Permit Status: Issued
Permit Number: T21CM06027
Permit Description: SFR STF40K T20-M0039
Total Completed Inspections - 23
Date Description Inspector Results Comments
09/14/2021 COT - RSPL - Sewer Passed {Activity date: 09/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/10/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled by contractor

}
09/14/2021 COT - RSPL - Rough Soil Passed {Activity date: 09/14/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/10/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled by contractor

}
09/24/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 09/24/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
09/24/2021 COT - RSBU - Preslab Passed {Activity date: 09/24/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
09/24/2021 COT - RSEL - Electrical Underground Passed {Activity date: 09/24/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
09/24/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 09/24/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
11/16/2021 COT - RSBU - Roof Nailing Passed {Activity date: 11/16/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
11/16/2021 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 11/16/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP}
02/07/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 02/07/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
02/07/2022 COT - LCBU - Framing Passed {Activity date: 02/07/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 11/16/2021; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - CO
Relieve all h2.5 hold downs and all shims from mid bearing point of trusses.
Trimmers are incorrect on 3 openings of same bearing wall.
Hallway opening cannot be less then 35 1/2” at rough frame.}
02/07/2022 RSME - Mechanical Progress Passed {Activity date: 02/07/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
02/07/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 02/07/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
02/16/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 02/09/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Inspection canceled by contractor

} ; {Activity date: 02/08/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Not ready} ; {Activity date: 02/07/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval pex lines at floor level not installed properly
Nail stop at dryer vent not installed properly
Toilet flanges not installed properly in 2 places}
02/16/2022 COT - RSPL - Yard Water Line Passed {Activity date: 02/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/14/2021; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. No text at this time; bury at own risk.} ; {Activity date: 09/10/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled by contractor

}
02/17/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 02/17/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
03/15/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 03/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - CODE ECO}
03/15/2022 COT - RSEL - Construction Power Passed {Activity date: 03/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved ok for clearance ECO}
04/21/2022 COT - BULD - SWG Clearance Passed {Activity date: 04/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS}
04/28/2022 COT - RSME - Mechanical Final Passed {Activity date: 04/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
04/28/2022 RSBU - Building Final Passed {Activity date: 04/28/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 04/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
04/28/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 04/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
04/28/2022 COT - RSPL - Plumbing Final Passed {Activity date: 04/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/21/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
SWG clearance required.} ; {Activity date: 07/26/2021; Status: Prior to Final Inspectn; Inspector: CVASQUE2; Comment: Entered by CVASQUE2 - SWR_SAGUARO TRAILS SQ20172860622 NWLY PTN BLOCK 6
SAGUARO TRAILS - BLOCK 6 - PHASE 1 - LOT 149 - ISSUED WITH $1,100.00 CONNECTION FEE DISCOUNT (CFD) PER SEWER SERVICE AGREEMENT AND PER PCRWRD/FRANCISCO GALINDO'S EMAIL DATED 6/2/21 - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD}
04/28/2022 COT - RSEL - Electrical Final Passed {Activity date: 04/28/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}

Documents

File Name Document Type  
JOB CARD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SITE PLAN.PDF CONSTRPLANS VIEW