Permit: T21CM06018
Permit Details
Apply Date:
07/23/2021
Applicant:
Andrea Flood
Description:
SFR F40G19 T19-M0038
Outstanding Activity Conditions
Permit Number - T21CM06018
Permit Status: Expired
Permit Description: SFR F40G19 T19-M0038
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
07/23/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
07/23/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
07/23/2021 | SWR_SAGUARO TRAILS SQ20172860622 NWLY PTN BLOCK 6SAGUARO TRAILS - BLOCK 6 - PHASE 1 - LOT 147 - ISSUED WITH $1,100.00 CONNECTION FEE DISCOUNT (CFD) PER SEWER SERVICE AGREEMENT AND PER PCRWRD/FRANCISCO GALINDO'S EMAIL DATED 6/2/21 - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM06018
Permit Description: SFR F40G19 T19-M0038
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/07/2021 | COT - RSPL - Sewer | Passed | {Activity date: 09/07/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved } |
|
09/07/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/07/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved } |
|
09/20/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/20/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved } |
|
09/20/2021 | COT - RSBU - Preslab | Passed | {Activity date: 09/20/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved } |
|
09/20/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/20/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved } |
|
09/20/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/20/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved } |
|
11/12/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 11/12/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 11/10/2021; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO Provide correct truss calc layout page for this plan.} |
|
11/12/2021 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 11/12/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 11/10/2021; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO Missing 3 anchor bolts at shear walls as noted on sill plate.} |
|
01/25/2022 | COT - LCBU - Framing | Passed | {Activity date: 01/25/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
01/26/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. Plumbing pex piping to close to recessed can lighting.} | |
01/26/2022 | RSME - Mechanical Progress | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
01/26/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
02/02/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 02/02/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
03/15/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 03/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - CODE ECO} | |
03/15/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 03/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved ok for clearance ECO} | |
04/14/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
04/20/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
04/20/2022 | RSBU - Building Final | Passed | {Activity date: 04/20/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
04/20/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 3090} ; {Activity date: 09/07/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval ok to cover} | |
04/20/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
04/20/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP SWG clearance required} ; {Activity date: 07/23/2021; Status: Prior to Final Inspectn; Inspector: CVASQUE2; Comment: Entered by CVASQUE2 - SWR_SAGUARO TRAILS SQ20172860622 NWLY PTN BLOCK 6 SAGUARO TRAILS - BLOCK 6 - PHASE 1 - LOT 147 - ISSUED WITH $1,100.00 CONNECTION FEE DISCOUNT (CFD) PER SEWER SERVICE AGREEMENT AND PER PCRWRD/FRANCISCO GALINDO'S EMAIL DATED 6/2/21 - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD} |
|
04/20/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 04/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} |