Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM05991
Permit Details
Apply Date:
07/22/2021
Applicant:
Kim Filuk/KDF Architectural Group
Description:
Layout and equipment modification to existing full service counter, sales floor, and checkstand.
Architects:
- KDF Architectural Group
Contractors:
- T BUILT LLC
Permit Reviews
Permit Number - T21CM05991
Permit Status: L of c
Permit Description: Layout and equipment modification to existing full service counter, sales floor, and checkstand.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/22/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/16/2021 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T21CM05991
Permit Description: Layout and equipment modification to existing full service counter, sales floor, and checkstand.
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2021 | PLUMBING - FINAL | PCAMARE | Approved | Water Chlorination Report required prior to Final Inspection |
12/16/2021 | ELECTRIC - PROGRESS | TGAUSP | Approved | NA |
12/16/2021 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | Partial for 5’ angled wall in Kitchen |
12/16/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | Partial for 5’ angled wall in Kitchen |
12/16/2021 | FRAMING | TGAUSP | Approved | Partial for 5’ angled wall in Kitchen |
12/20/2021 | PLUMBING - PROGRESS | JBURGE | Approved | Partial. Waste and vent lines (underground) in kitchen area. Ok to cover progress areas. |
01/11/2022 | FIRE - FINAL | MRoss | Approved | Mount fire extinguisher on wall in back room. |
01/18/2022 | BUILDING - FINAL | RSHERRY | Approved | |
01/18/2022 | MECHANICAL - FINAL | RSHERRY | Approved | EXHAUST HOOD OPERATIONAL |
01/18/2022 | BUILDING - FINAL | TGAUSP | Approved | Partial, pending mechanical |
01/18/2022 | MECHANICAL - FINAL | TGAUSP | Approved | Partial, hood exhaust is operational, pending correction on report |
01/18/2022 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
01/19/2022 | MECHANICAL - PROGRESS | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | MECHANICAL - ABOVE CEILING | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | BUILDING - PROGRESS | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | SHEET ROCK NAILING | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | BUILDING ABOVE CEILING | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | ELECTRIC - ABOVE CEILING | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | PLUMBING - ABOVE CEILING | JG3 | Approved | This inspection approved based on Final Inspection. |
01/19/2022 | MECHANICAL - INTERMEDIATE | JG3 | Approved | This inspection approved based on Final Inspection. |