Permit: T21CM05945
Permit Details
Apply Date:
07/21/2021
Applicant:
MARION DIANE BONAPARTE
Description:
THIS PROJECT INVOLVES THE INSTALLATION OF A GRID-INTERACTIVE PV SYSTEM. PV MODULES WILL BE MOUNTED USING A PRE-ENGINEERED MOUNTING SYSTEM. THE MODULES WILL BE ELECTRICALLY CONNECTED WITH DC TO AC POWER INVERTERS AND INTERCONNECTED TO THE LOCAL UTILITY USING MEANS AND METHODS CONSISTENT WITH THE RULES ENFORCED BY THE LOCAL UTILITY AND PERMITTING JURISDICTION.
Contractors:
- MARION DIANE BONAPARTE
Permit Reviews
Permit Number - T21CM05945
Permit Status: Final
Permit Description: THIS PROJECT INVOLVES THE INSTALLATION OF A GRID-INTERACTIVE PV SYSTEM. PV MODULES WILL BE MOUNTED USING A PRE-ENGINEERED MOUNTING SYSTEM. THE MODULES WILL BE ELECTRICALLY CONNECTED WITH DC TO AC POWER INVERTERS AND INTERCONNECTED TO THE LOCAL UTILITY
USING MEANS AND METHODS CONSISTENT WITH THE RULES ENFORCED BY THE LOCAL UTILITY AND PERMITTING JURISDICTION.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/21/2021 | OTHER | 08/09/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM05945
Permit Description: THIS PROJECT INVOLVES THE INSTALLATION OF A GRID-INTERACTIVE PV SYSTEM. PV MODULES WILL BE MOUNTED USING A PRE-ENGINEERED MOUNTING SYSTEM. THE MODULES WILL BE ELECTRICALLY CONNECTED WITH DC TO AC POWER INVERTERS AND INTERCONNECTED TO THE LOCAL UTILITY
USING MEANS AND METHODS CONSISTENT WITH THE RULES ENFORCED BY THE LOCAL UTILITY AND PERMITTING JURISDICTION.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/14/2021 | TEP CLEARANCE - AM | RCHANDLER | Approved | CODE DGC |
| 12/14/2021 | ELECTRIC - FINAL | RCHANDLER | Approved | AP. DGC clearance for TEP. |
| 12/14/2021 | BUILDING - FINAL | RCHANDLER | Approved | -AP |
| 12/14/2021 | ELECTRIC - FINAL | RCHANDLER | Approved | DE. Install labels at meter and PV breaker. |
| 12/14/2021 | BUILDING - FINAL | RCHANDLER | Approved | DE. Obtain 2090 inspection approval. |