Permit: T21CM05927
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
4842 S BENTLEY AV
Address NEW:
4842 S BENTLEY AV
Apply Date:
07/21/2021
Applicant:
Diane Krebs
Description:
Single Family Residence
Permit Reviews
Permit Number - T21CM05927
Permit Status: Complete
Permit Description: Single Family Residence
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/21/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/17/2021 | COMPLETED |
| 08/24/2021 | RESUBMITTAL | 09/01/2021 | COMPLETED |
Conditions
Permit Number - T21CM05927
Permit Status: Complete
Permit Description: Single Family Residence
| Date | Description | Comments |
|---|---|---|
| 09/01/2021 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
| 09/01/2021 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM05927
Permite Description: Single Family Residence
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Sewer | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Yard Water Line | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM05927
Permit Description: Single Family Residence
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/07/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 12/07/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 12/21/2021 | COT - RSBU - Preslab | Passed | {Activity date: 12/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 12/21/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 02/15/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 02/15/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 03/08/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 03/08/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO} | |
| 03/08/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 03/08/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, please send ECO Clearance to TEP for the construction power } ; {Activity date: 03/04/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - corrections required, install Grounding Electrode Conductor from ground rods to panel, install permanent address label, provide weatherproof GFCI outlet.} |
|
| 08/02/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 12/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 08/02/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
| 08/02/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
| 08/02/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
| 09/15/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 08/02/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Correction required. Provide fire foam on all top penetrations. Provide fan rated boxes and make sure ground screw is in.} | |
| 09/15/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 08/02/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Correction required. Provide plans on details of glue lamb header board.} ; {Activity date: 02/15/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - correction required, change out Patio and carport Glu lam beams from 6” to 9” per plan.} | |
| 09/16/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 07/10/2023 | COT - RSEL - Outdoor Lighting | Passed | porch lights are installed and meet city requirements | |
| 07/10/2023 | COT - RSPL - Sewer | Passed | Passed 12/7/22 | |
| 07/10/2023 | COT - RSPL - Yard Water Line | Passed | Passed 12/7/22 | |
| 07/10/2023 | COT - RSEL - Electrical Final | Passed | Electrical panel is properly labeled. AFCI breakers are installed for bedrooms and GFCI outlets are installed for bathroom, kitchen, and exterior of home. | |
| 07/10/2023 | COT - RSME - Mechanical Final | Passed | Mechanical equipment is installed and properly working. A/C registers and returns are installed throughout. | |
| 07/10/2023 | COT - RSPL - Plumbing Final | Passed | Plumbing fixtures are installed and properly working. | |
| 07/10/2023 | RSBU - Building Final | Passed | Building construction, mechanical, electrical, and plumbing are complete. Okay to issue Certificate of Occupancy. |