Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address NEW:
4842 S BENTLEY AV
Apply Date:
07/21/2021
Applicant:
Diane Krebs
Description:
Single Family Residence

Permit Reviews

Permit Number - T21CM05927
Permit Status: Complete
Permit Description: Single Family Residence
Start Date Submittal Complete Date Status  
07/21/2021 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 08/17/2021 COMPLETED Review Details
08/24/2021 RESUBMITTAL 09/01/2021 COMPLETED Review Details

Conditions

Permit Number - T21CM05927
Permit Status: Complete
Permit Description: Single Family Residence
Date Description Comments
09/01/2021 This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm
09/01/2021 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS.

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM05927
Permite Description: Single Family Residence
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - RSEL - Outdoor Lighting N/A Not Ready
10/26/2022 COT - RSPL - Sewer N/A Not Ready
10/26/2022 COT - RSPL - Yard Water Line N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T21CM05927
Permit Description: Single Family Residence
Total Completed Inspections - 21
Date Description Inspector Results Comments
12/07/2021 COT - RSPL - Rough Soil Passed {Activity date: 12/07/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
12/21/2021 COT - RSBU - Preslab Passed {Activity date: 12/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
12/21/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 12/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
02/15/2022 COT - RSBU - Roof Nailing Passed {Activity date: 02/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
02/15/2022 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 02/15/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
03/08/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO}
03/08/2022 COT - RSEL - Construction Power Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, please send ECO Clearance to TEP for the construction power

} ; {Activity date: 03/04/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - corrections required, install Grounding Electrode Conductor from ground rods to panel, install permanent address label, provide weatherproof GFCI outlet.}
08/02/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 12/21/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
08/02/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved}
08/02/2022 RSME - Mechanical Progress Passed {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved}
08/02/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 08/02/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved}
09/15/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 09/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 08/02/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Correction required. Provide fire foam on all top penetrations. Provide fan rated boxes and make sure ground screw is in.}
09/15/2022 COT - LCBU - Framing Passed {Activity date: 09/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 08/02/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - partial. Correction required. Provide plans on details of glue lamb header board.} ; {Activity date: 02/15/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by VVERA1 - correction required, change out Patio and carport Glu lam beams from 6” to 9” per plan.}
09/16/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 09/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
07/10/2023 COT - RSEL - Outdoor Lighting Passed porch lights are installed and meet city requirements
07/10/2023 COT - RSPL - Sewer Passed Passed 12/7/22
07/10/2023 COT - RSPL - Yard Water Line Passed Passed 12/7/22
07/10/2023 COT - RSEL - Electrical Final Passed Electrical panel is properly labeled. AFCI breakers are installed for bedrooms and GFCI outlets are installed for bathroom, kitchen, and exterior of home.
07/10/2023 COT - RSME - Mechanical Final Passed Mechanical equipment is installed and properly working. A/C registers and returns are installed throughout.
07/10/2023 COT - RSPL - Plumbing Final Passed Plumbing fixtures are installed and properly working.
07/10/2023 RSBU - Building Final Passed Building construction, mechanical, electrical, and plumbing are complete. Okay to issue Certificate of Occupancy.

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
HVAC CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TRUSS CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TRUSS LAYOUT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
HVAC CALCS.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
TRUSS CALCS.PDF DOCUMENTS VIEW
TRUSS LAYOUT.PDF DOCUMENTS VIEW