Permit: T21CM05924
Permit Details
Apply Date:
07/21/2021
Applicant:
Russ Salmon
Description:
SFR LENNVC354 T20-M0030
Outstanding Activity Conditions
Permit Number - T21CM05924
Permit Status: Issued
Permit Description: SFR LENNVC354 T20-M0030
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
07/21/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
07/21/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM05924
Permit Description: SFR LENNVC354 T20-M0030
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/08/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 09/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved } |
|
09/08/2021 | COT - RSPL - Sewer | Passed | {Activity date: 09/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved } |
|
09/08/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved } |
|
09/14/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
09/14/2021 | COT - RSBU - Preslab | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
09/14/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
09/14/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
10/14/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
10/14/2021 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
02/16/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO} | |
02/16/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved clear TEP ECO} | |
02/17/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - . AP} | |
02/17/2022 | COT - LCBU - Framing | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - . AP} | |
02/17/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - . AP} | |
02/17/2022 | RSME - Mechanical Progress | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - . AP} | |
02/17/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - . AP} | |
03/07/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 03/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/12/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 05/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE} | |
05/17/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/17/2022 | RSBU - Building Final | Passed | {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/17/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/17/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, clear southwest gas} | |
05/17/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 05/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} |