Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
07/20/2021
Applicant:
Description:
SFR LENNVC453 T20-M0036

Outstanding Activity Conditions

Permit Number - T21CM05902
Permit Status: Issued
Permit Description: SFR LENNVC453 T20-M0036
Total Outstanding Activity Conditions - 2
Date Name
07/20/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
07/20/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Issued
Permit Number: T21CM05902
Permit Description: SFR LENNVC453 T20-M0036
Total Completed Inspections - 23
Date Description Inspector Results Comments
09/08/2021 COT - RSPL - Yard Water Line Passed {Activity date: 09/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
09/08/2021 COT - RSPL - Sewer Passed {Activity date: 09/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
09/08/2021 COT - RSPL - Rough Soil Passed {Activity date: 09/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
09/17/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 09/17/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/17/2021 COT - RSBU - Preslab Passed {Activity date: 09/17/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/17/2021 COT - RSEL - Electrical Underground Passed {Activity date: 09/17/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/17/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 09/17/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
10/22/2021 COT - RSBU - Roof Nailing Passed {Activity date: 10/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/20/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 10/18/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready}
10/22/2021 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 10/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/20/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 10/18/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready}
02/15/2022 COT - LCBU - Framing Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/15/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/15/2022 RSME - Mechanical Progress Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/15/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 02/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/17/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 02/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 02/15/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO. Vents dry, missing several nail plates}
03/08/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/11/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 03/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO}
03/11/2022 COT - RSEL - Construction Power Passed {Activity date: 03/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP
TEP ECO

} ; {Activity date: 03/10/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR}
04/25/2022 COT - RSPL - Plumbing Final Passed {Activity date: 04/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
SWG clearance required}
04/25/2022 COT - BULD - SWG Clearance Passed {Activity date: 04/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS}
05/16/2022 COT - RSME - Mechanical Final Passed {Activity date: 05/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
05/16/2022 RSBU - Building Final Passed {Activity date: 05/16/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - APPROVED BY INSPECTOR AWAITING CONDITIONS
} ; {Activity date: 05/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
05/16/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 05/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - 1090.Approved}
05/16/2022 COT - RSEL - Electrical Final Passed {Activity date: 05/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}