Permit: T21CM05865
Permit Details
Apply Date:
07/19/2021
Applicant:
Hugh O'Malley
Description:
ADDDITION AND RELOCATE GARAGE
Permit Reviews
Permit Number - T21CM05865
Permit Status: Issued
Permit Description: ADDDITION AND RELOCATE GARAGE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/19/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/12/2021 | COMPLETED |
08/13/2021 | RESUBMITTAL | 08/16/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM05865
Permit Status: Issued
Permit Description: ADDDITION AND RELOCATE GARAGE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/19/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T21CM05865
Permit Status: Issued
Permit Description: ADDDITION AND RELOCATE GARAGE
Date | Description | Comments |
---|---|---|
08/08/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM05865
Permite Description: ADDDITION AND RELOCATE GARAGE
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
10/26/2022 | COT - RSPL - Rough Soil | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
05/17/2023 | COT - RSME - Mechanical Final | N/A | Canceled | not ready just extending permit time line |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM05865
Permit Description: ADDDITION AND RELOCATE GARAGE
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2022 | COT - RSBU - Stem Wall/Retaining Wall | Passed | {Activity date: 04/28/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
04/28/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 04/28/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
05/27/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
06/30/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 06/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR} | |
06/30/2022 | COT - RSEL - Service Upgrade | Passed | {Activity date: 06/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Need cutover for final Clear incr } |
|
08/09/2022 | COT - RSBU - Masonry Pregrout | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Top out.} ; {Activity date: 08/02/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Patio wall ok for first lift, interior partition wall at SE corner ok for 1st lift } ; {Activity date: 07/06/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -PA. Top out of exterior walls of house; porch and interior portion remain to be inspected. } ; {Activity date: 06/21/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Garage top out ok to grout. House 3rd lift ok to grout. } ; {Activity date: 06/03/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. 2nd lift. 4 to 8 feet.} ; {Activity date: 05/27/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa 1st lift ok to grout} |
|
10/18/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/17/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 09/29/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval waiting on patio cover} ; {Activity date: 07/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
10/18/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/29/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval waiting on patio cover} ; {Activity date: 08/09/2022; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Not ready.} | |
12/01/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
12/01/2022 | COT - LCBU - Framing | Passed | ||
12/01/2022 | COT - LCPL - Plumbing Roof Drains | Passed | ||
12/01/2022 | RSME - Mechanical Progress | Passed | ||
12/01/2022 | COT - RSPL - Gas Pressure Test | Passed | ||
05/16/2024 | COT - BULD - SWG Clearance | Passed | Verbal clearance to Southwest Gas. 5/16/2024 |