Permit: T21CM05851
Permit Details
Apply Date:
07/16/2021
Applicant:
N/A
Description:
RESTAURANT/DRIVE THRU
Architects:
- Dan Winter
Contractors:
- BOBBY PONTIUS
Permit Reviews
Permit Number - T21CM05851
Permit Status: C of o
Permit Description: RESTAURANT/DRIVE THRU
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/05/2022 | RESUBMITTAL | 02/04/2022 | COMPLETED |
02/24/2022 | REVISION - - 1ST | 04/29/2022 | COMPLETED |
07/16/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/20/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM05851
Permit Description: RESTAURANT/DRIVE THRU
Total Completed Inspections - 49
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/18/2022 | SITE - SEWER | DMUNIZ | Approved | Approved, site sewer installed from road to waste/interceptor locations. |
02/23/2022 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | Approved |
03/03/2022 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
03/03/2022 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
03/03/2022 | PLUMBING - PRE SLAB | DMUNIZ | Approved | Approved |
03/22/2022 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | Approved |
03/24/2022 | ROOF NAILING | JBURGE | Approved | Approved. Ok to dry-in roof system. |
04/19/2022 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | Approved |
04/25/2022 | PLUMBING - ROOF DRAINS | DQUINN | Approved | Ap |
05/06/2022 | FRAMING | JBURGE | Approved | Approved. Ok to insulate and cover walls. |
05/09/2022 | PLUMBING - ABOVE CEILING | WGALLAGHER | Approved | Approved |
05/24/2022 | GAS CLEARANCE | DQUINN | Approved | CODE CAS |
05/24/2022 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | was approved on 4/25 Please clear gas |
06/21/2022 | MECHANICAL - PROGRESS | WGALLAGHER | Approved | Approved |
07/11/2022 | ELECTRIC - UNDERGROUND | JBURGE | Approved | Approved. Power conduits for menu board |
07/11/2022 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Approved. Menu board caisson footings. Ok to place concrete in progress areas. |
07/13/2022 | MECHANICAL - HOOD SYSTEMS | JBURGE | Approved | Approved. Grease ducts are double wrapped and secured in place. |
07/19/2022 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO |
07/25/2022 | STEM WALL/RETAINING WALL | JBURGE | Approved | Approved. South stem wall at 5’4” X 30’. Ok to place grout in progress areas. |
07/27/2022 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved. 0k to set ceiling tiles. |
07/27/2022 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Approved |
07/27/2022 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | Approved |
08/03/2022 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
08/09/2022 | MECHANICAL - FINAL | JBURGE | Approved | Approved. Air balance test results forwarded to Robert Sherry. |
08/09/2022 | MECHANICAL - HOODS | JBURGE | Approved | Approved |
08/09/2022 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | Approved |
08/09/2022 | ELECTRIC - PROGRESS | JBURGE | Approved | Approved |
08/09/2022 | PLUMBING - PROGRESS | JBURGE | Approved | Approved |
08/09/2022 | PLUMBING - FINAL | JBURGE | Approved | Approved. Bacteria test results forwarded to Robert Sherry |
08/09/2022 | PLUMBING - BACK WATER VALVE | JBURGE | Approved | Approved |
08/09/2022 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | Approved |
08/09/2022 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Approved |
08/09/2022 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved |
08/09/2022 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
08/09/2022 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | Approved |
08/09/2022 | BUILDING - PROGRESS | JBURGE | Approved | Approved |
08/09/2022 | SHEET ROCK NAILING | JBURGE | Approved | Approved |
08/09/2022 | U VALUE FOR WINDOW | JBURGE | Approved | Approved |
08/09/2022 | STUCCO MESH | JBURGE | Approved | Approved |
08/09/2022 | BUILDING ABOVE CEILING | JBURGE | Approved | Approved |
08/09/2022 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | Approved |
08/09/2022 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | Approved |
08/11/2022 | FIRE - FINAL | CGates | Approved | |
08/15/2022 | LANDSCAPE - FINAL | MERNANDEZ | Approved | APPROVED |
08/15/2022 | ENGINEERING - FINAL | MERNANDEZ | Approved | APPROVED |
08/15/2022 | SIGN - FINAL | MERNANDEZ | Approved | APPROVED |
08/17/2022 | HEALTH DEPT - FINAL 724-7908 | JG3 | Approved | |
09/27/2022 | RIGHT OF WAY - FINAL | Bravin | Approved | ROW final completed. no issues |
10/19/2022 | BUILDING - FINAL | JBURGE | Approved |