Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
07/16/2021
Applicant:
N/A
Description:
RESTAURANT/DRIVE THRU
Architects:
  • Dan Winter
Contractors:
  • BOBBY PONTIUS

Permit Reviews

Permit Number - T21CM05851
Permit Status: C of o
Permit Description: RESTAURANT/DRIVE THRU
Start Date Submittal Complete Date Status  
01/05/2022 RESUBMITTAL 02/04/2022 COMPLETED Review Details
02/24/2022 REVISION - - 1ST 04/29/2022 COMPLETED Review Details
07/16/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 08/20/2021 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T21CM05851
Permit Description: RESTAURANT/DRIVE THRU
Total Completed Inspections - 49
Date Description Inspector Results Comments
02/18/2022 SITE - SEWER DMUNIZ Approved Approved, site sewer installed from road to waste/interceptor locations.
02/23/2022 PLUMBING - YARD WTR LINE/TEST ESTEVENS Approved Approved
03/03/2022 BUILDING PRE-SLAB DMUNIZ Approved Approved
03/03/2022 ELECTRIC - UFER DMUNIZ Approved Approved
03/03/2022 PLUMBING - PRE SLAB DMUNIZ Approved Approved
03/22/2022 PLUMBING - SEWER HCS CONNECT ESTEVENS Approved Approved
03/24/2022 ROOF NAILING JBURGE Approved Approved. Ok to dry-in roof system.
04/19/2022 ELECTRIC - INTERMEDIATE ESTEVENS Approved Approved
04/25/2022 PLUMBING - ROOF DRAINS DQUINN Approved Ap
05/06/2022 FRAMING JBURGE Approved Approved. Ok to insulate and cover walls.
05/09/2022 PLUMBING - ABOVE CEILING WGALLAGHER Approved Approved
05/24/2022 GAS CLEARANCE DQUINN Approved CODE CAS
05/24/2022 PLUMBING - GAS PRESSURE TEST DQUINN Approved was approved on 4/25

Please clear gas
06/21/2022 MECHANICAL - PROGRESS WGALLAGHER Approved Approved
07/11/2022 ELECTRIC - UNDERGROUND JBURGE Approved Approved. Power conduits for menu board
07/11/2022 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved Approved. Menu board caisson footings. Ok to place concrete in progress areas.
07/13/2022 MECHANICAL - HOOD SYSTEMS JBURGE Approved Approved. Grease ducts are double wrapped and secured in place.
07/19/2022 TEP CLEARANCE - PM WGALLAGHER Approved CODE ECO
07/25/2022 STEM WALL/RETAINING WALL JBURGE Approved Approved. South stem wall at 5’4” X 30’. Ok to place grout in progress areas.
07/27/2022 MECHANICAL - INTERMEDIATE JBURGE Approved Approved. 0k to set ceiling tiles.
07/27/2022 PLUMBING - INTERMEDIATE JBURGE Approved Approved
07/27/2022 ELECTRIC - ABOVE CEILING JBURGE Approved Approved
08/03/2022 FIRE - KITCHEN EXH HOOD FINAL CBASALDUA Approved
08/09/2022 MECHANICAL - FINAL JBURGE Approved Approved. Air balance test results forwarded to Robert Sherry.
08/09/2022 MECHANICAL - HOODS JBURGE Approved Approved
08/09/2022 MECHANICAL - ABOVE CEILING JBURGE Approved Approved
08/09/2022 ELECTRIC - PROGRESS JBURGE Approved Approved
08/09/2022 PLUMBING - PROGRESS JBURGE Approved Approved
08/09/2022 PLUMBING - FINAL JBURGE Approved Approved. Bacteria test results forwarded to Robert Sherry
08/09/2022 PLUMBING - BACK WATER VALVE JBURGE Approved Approved
08/09/2022 PLUMBING - GAS PRESS TEST FNL JBURGE Approved Approved
08/09/2022 PLUMBING - ROUGH, SOIL JBURGE Approved Approved
08/09/2022 OUTDOOR LIGHTING FINAL JBURGE Approved Approved
08/09/2022 ELECTRIC - FINAL JBURGE Approved Approved
08/09/2022 ELECTRIC - OUTDOOR LIGHTING JBURGE Approved Approved
08/09/2022 BUILDING - PROGRESS JBURGE Approved Approved
08/09/2022 SHEET ROCK NAILING JBURGE Approved Approved
08/09/2022 U VALUE FOR WINDOW JBURGE Approved Approved
08/09/2022 STUCCO MESH JBURGE Approved Approved
08/09/2022 BUILDING ABOVE CEILING JBURGE Approved Approved
08/09/2022 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved Approved
08/09/2022 REINFORCED MASONRY PRE-GROUT JBURGE Approved Approved
08/11/2022 FIRE - FINAL CGates Approved
08/15/2022 LANDSCAPE - FINAL MERNANDEZ Approved APPROVED
08/15/2022 ENGINEERING - FINAL MERNANDEZ Approved APPROVED
08/15/2022 SIGN - FINAL MERNANDEZ Approved APPROVED
08/17/2022 HEALTH DEPT - FINAL 724-7908 JG3 Approved
09/27/2022 RIGHT OF WAY - FINAL Bravin Approved ROW final completed. no issues
10/19/2022 BUILDING - FINAL JBURGE Approved

Documents

File Name Document Type  
C OF O 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TCO 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
C OF O.PDF DOCUMENTS VIEW
TCO.PDF DOCUMENTS VIEW
COMCHECK.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
COMCHECK_LIGHTING.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW
JOB CARD.PDF DOCUMENTS VIEW
REV1_REVISION NARRATIVE.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF CONSTRPLANS VIEW