Permit: T21CM05753
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
124 E BROADWAY BL
Address NEW:
124 E BROADWAY BL
Apply Date:
07/14/2021
Applicant:
Tucson Expediting & Development
Description:
Renovation of Existing building into apartments and retail spaces
Architects:
- William Williams
Contractors:
- A Karic Consulting
Permit Reviews
Permit Number - T21CM05753
Permit Status: C of o
Permit Description: Renovation of Existing building into apartments and retail spaces
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/14/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/09/2021 | COMPLETED |
| 08/25/2021 | RESUBMITTAL | 09/03/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM05753
Permit Description: Renovation of Existing building into apartments and retail spaces
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2021 | PLUMBING - FINAL | PCAMARE1 | Approved | Water Chlorination Report required prior to Final Inspection |
| 09/02/2021 | MECHANICAL - FINAL | PCAMARE1 | Approved | Air Balance Report required prior to Final Inspection |
| 09/29/2021 | FRAMING | JBURGE | Approved | Approved. Level #1 and basement areas. Ok to insulate and cover walls |
| 12/07/2021 | MECHANICAL - HOODS | JBURGE | Approved | N/A |
| 12/07/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | Approved |
| 12/07/2021 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | Approved |
| 12/07/2021 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | Approved |
| 12/07/2021 | ELECTRIC - PROGRESS | JBURGE | Approved | Approved |
| 12/07/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Approved |
| 12/07/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Approved |
| 12/07/2021 | MECHANICAL - PROGRESS | JBURGE | Approved | Approved |
| 12/07/2021 | SHEET ROCK NAILING | JBURGE | Approved | Approved |
| 12/07/2021 | PLUMBING - ABOVE CEILING | JBURGE | Approved | Approved |
| 12/07/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved |
| 12/07/2021 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | Approved |
| 12/07/2021 | BUILDING PRE-SLAB | JBURGE | Approved | Approved |
| 12/07/2021 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | Approved |
| 12/07/2021 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved |
| 12/07/2021 | PLUMBING - PRE SLAB | JBURGE | Approved | |
| 12/07/2021 | PLUMBING - PROGRESS | JBURGE | Approved | Approved |
| 02/03/2022 | TEP CLEARANCE - PM | JBURGE | Approved | CODE INCR |
| 02/03/2022 | ELECTRIC - FINAL | JBURGE | Approved | Approved. Service upgrade to 800 amp service. Power kill complete; Ok to energize system. CLEARANCE: Code: INCR. Called in to TEP at 1110 hours. |
| 02/11/2022 | BUILDING - PROGRESS | JBURGE | Approved | Approved |
| 02/15/2022 | FIRE - FINAL | wmotto | Approved | |
| 02/15/2022 | FIRE - ALARM FINAL | wmotto | Approved | |
| 02/15/2022 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 02/16/2022 | GAS CLEARANCE | JBURGE | Approved | CODE |
| 02/17/2022 | BUILDING - FINAL | JBURGE | Approved | |
| 02/17/2022 | BUILDING - FINAL | JBURGE | Approved | AP, PENDING FIRE FINALS AND SPECIAL INSPECTIONS |