Permit: T21CM05585
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
5511 E SOUTH WILSHIRE DR
Address NEW:
5511 E SOUTH WILSHIRE DR
Apply Date:
07/08/2021
Applicant:
Description:
Ramada
Permit Reviews
Permit Number - T21CM05585
Permit Status: Issued
Permit Description: Ramada
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/08/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/18/2021 | COMPLETED |
| 09/21/2021 | RESUBMITTAL | 09/30/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM05585
Permite Description: Ramada
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2022 | COT - LCBU - Framing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - RSEL - Electrical Final | N/A | Canceled | Inspection Canceled |
| 11/07/2022 | COT - RSPL - Plumbing Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM05585
Permit Description: Ramada
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/21/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/21/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 03/31/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 03/31/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP. No clearance needed.} ; {Activity date: 02/01/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Sent text at 10:51 After noon. 1:00 1:08; NR. Contractor thought it was an on site inspection; will attempt to get someone with a phone to contact me. 415-806-6286 is on site contact. 1:45 1:49; unable to connect with FaceTime nor Duo. } ; {Activity date: 01/31/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -CA per text from contractor.} |
|
| 06/14/2023 | COT - RSBU - Roof Nailing | Passed | Metal roof is properly screwed off to roof rafters. | |
| 06/14/2023 | RSBU - Building Final | Passed | Ramada, Gas-line connection and electrical outlets being complete. | |
| 06/14/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Column post, beams, purlins, and rafters are properly connected with screws connecting from the top. | |
| 06/14/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Gas line for outdoor fire pit is properly installed and operational. Electrical for ceiling fans and outdoor barbecue island is properly installed with GFCI breakers in electrical panel. |