Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
2945 N BEAR CANYON RD
Apply Date:
07/02/2021
Applicant:
Jim Morrison
Description:
New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe

Permit Reviews

Permit Number - T21CM05449
Permit Status: Issued
Permit Description: New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe
Start Date Submittal Complete Date Status  
02/10/2022 RESUBMITTAL 03/04/2022 COMPLETED Review Details
07/02/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 08/16/2021 COMPLETED Review Details
08/25/2021 RESUBMITTAL 09/28/2021 COMPLETED Review Details
11/01/2021 RESUBMITTAL 02/10/2022 COMPLETED Review Details
09/24/2025 COMMERCIAL REVIEW - FULL v.2 10/14/2025 APPROVED Review Details
09/27/2024 COMMERCIAL REVIEW - FULL v.2 10/11/2024 REQUIRES RESUBMIT Review Details
07/23/2025 COMMERCIAL REVIEW - FULL v.1 08/13/2025 REQUIRES RESUBMIT Review Details
10/11/2024 RESTAMP - COMMERCIAL v.1 10/14/2024 APPROVED Review Details
07/21/2023 COMMERCIAL REVIEW - FULL v.1 08/21/2023 REQUIRES RESUBMIT Review Details
10/14/2025 RESTAMP - COMMERCIAL v.1 10/16/2025 APPROVED Review Details
05/07/2026 COMMERCIAL REVIEW - FULL REVISION v.1 05/29/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T21CM05449
Permit Status: Issued
Permit Description: New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe
Total Outstanding Activity Conditions - 13
Date Name
07/09/2025 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
07/09/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/09/2025 SHOP DRAWINGS REQUIRED FOR AUTOMATIC FIRE SPRINKLERS.
07/09/2025 SHOP DRAWINGS REQUIRED FOR CARPORT STRUCTURE.
07/09/2025 SHOP DRAWINGS REQUIRED FOR FIRE ALARM MONITORING.
07/09/2025 SHOP DRAWINGS REQUIRED FOR PRE-ENGINEERED RAMADAS.
07/09/2025 SHOP DRAWINGS REQUIRED FOR PRE-ENGINEERED WOOD TRUSSES.
07/09/2025 SHOP DRAWINGS REQUIRED FOR STEEL STAIRS.
07/09/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/09/2025 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
07/09/2025 SPECIAL INSPECTION FOR SHOTCRETE IS REQUIRED.
07/09/2025 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
07/09/2025 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.

Conditions

Permit Number - T21CM05449
Permit Status: Issued
Permit Description: New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe
Date Description Comments
02/18/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM05449
Permite Description: New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe
Total Outstanding Inspections - 46
Last Inspection Date Description Inspector Results Comments
11/04/2022 COT - LCPL - Gas Pressure Test N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Building Above Ceiling N/A Canceled Inspection Canceled
11/04/2022 COT - LCEL - Electrical Progress N/A Canceled Inspection Canceled
11/04/2022 COT - LCEL - Electrical Intermediate N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Framing N/A Canceled Inspection Canceled
11/04/2022 COT - LCEL - Electrical Underground N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Plumbing Progress N/A Canceled Inspection Canceled
11/04/2022 COT - LCME - Mechanical Above Ceiling N/A Canceled Inspection Canceled
11/04/2022 COT - LCME - Mechanical Progress N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Excavation/Rebar/Zoning N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Firewall/Fire Barrier/Firestop N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Plumbing Roof Drains N/A Canceled Inspection Canceled
11/04/2022 COT - LCME - Kitchen Hood N/A Canceled Inspection Canceled
11/04/2022 COT - LCEL - Outdoor Lighting N/A Canceled Inspection Canceled
11/04/2022 Pool/Spa - Electric N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Preslab N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Plumbing Intermediate N/A Canceled Inspection Canceled
11/04/2022 Pool/Spa - Bonding Grip N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Exterior Clips/Sheathing N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Plumbing Above Ceiling N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Sustainability N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Rough Soil N/A Canceled Inspection Canceled
11/04/2022 COT - LCEL - Electrical Above Ceiling N/A Canceled Inspection Canceled
11/04/2022 COT - LCME - Mechanical Intermediate N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Roof Nailing N/A Canceled Inspection Canceled
11/04/2022 COT - LCBU - Building Progress N/A Canceled Inspection Canceled
11/04/2022 Pool/Spa - Heater N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Sewer N/A Canceled Inspection Canceled
11/04/2022 Pool/Spa - Plumbing N/A Canceled Inspection Canceled
11/04/2022 COT - HCBU - Interior Shear Bracing N/A Canceled Inspection Canceled
11/04/2022 COT - LCPL - Backwater Valve N/A Canceled Inspection Canceled
12/17/2025 COT - HCME - Kitchen Hood N/A Not Applicable
12/17/2025 COT - HCME - Venting N/A Not Applicable
12/17/2025 Pool/Spa - Final/Barrier N/A Not Applicable part of pool permit
09/26/2025 COT - HCME - Mechanical Intermediate N/A Partial Pass Pre-slab.
02/03/2026 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable
12/04/2025 COT - HCBU - Framing N/A Not Ready Complete MEP rough in's and dry in.
12/04/2025 COT - HCPL - Yard Water Line N/A Partial Pass building entry
06/26/2026 BULD - Electrical Clearance N/A Partial Pass ok for TEP to pull primaries.
TRSP - ROW - Final/Close-Out N/A Scheduled
06/24/2026 COT - LCEL - Electrical Final N/A Not Ready
09/17/2026 ENGR Engineering Final N/A Partial Pass Okay to apply for TCO level 1
09/17/2026 COT - LCPL - Plumbing Final N/A Not Ready
09/17/2026 COT - LCBU - Building Final N/A Partial Pass
09/17/2026 COT - LCME - Mechanical Final N/A Not Ready
09/17/2026 COT - HCPL - Backwater Valve N/A Not Applicable

Completed Inspections

Permit Status: Issued
Permit Number: T21CM05449
Permit Description: New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe
Total Completed Inspections - 23
Date Description Inspector Results Comments
09/16/2025 FCON – Fire – Intermediate Passed Riser sweep inspection.
12/04/2025 COT - HCBU - Exterior Clips/Sheathing Passed
12/04/2025 COT - HCBU - Roof Nailing Passed
12/04/2025 COT - HCBU - Excavation/Rebar/Zoning Passed
12/04/2025 COT - HCEL - Grounding/Bonding Passed
12/04/2025 COT - HCEL - Electrical Underground Passed
12/16/2025 COT - HCPL - Plumbing Roof Drains Passed
12/17/2025 COT - HCBU - Preslab Passed
12/18/2025 COT - HCBU - Building Progress Passed
01/15/2026 COT - HCME - Mechanical Intermediate Passed
02/03/2026 COT - HCEL - Electrical Intermediate Passed
02/03/2026 COT - HCBU - Framing Passed
02/03/2026 COT - HCPL - Plumbing Intermediate Passed
03/25/2026 COT - HCPL - Rough Soil Passed
04/24/2026 COT - HCPL - Sewer Passed Passed 4/24/26
05/05/2026 COT - HCPL - Gas Pressure Test Passed
05/05/2026 COT - HCPL - Yard Water Line Passed
05/28/2026 COT - BULD - SWG Clearance Passed
09/17/2026 COT - FCON - Fire - Final Passed
09/17/2026 COT - HCEL - Outdoor Lighting Passed
09/17/2026 COT - HCPL - Gas Final Passed
09/17/2026 COT - FCON - Alarm - Final Passed
09/17/2026 COT - FCON - Sprinkler - Final Passed

Scheduled Inspections

Scheduled Inspections - T21CM05449
Status: Issued
Description: New 256 unit apartment complex. There are 18 buildings.Each building has been assigned a separate pe
Scheduled Date Description Entered By Entered Date
09/21/2026 TRSP - ROW - Final/Close-Out Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .