Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Address NEW:
1625 W ONTARIO ST 01
Apply Date:
06/30/2021
Applicant:
Lisa Bowers
Description:
Fire Damage Repair for 935 SF of existing residence and replacing roof structure over Unit B

Completed Inspections

Permit Status: Issued
Permit Number: T21CM05392
Permit Description: Fire Damage Repair for 935 SF of existing residence and replacing roof structure over Unit B
Total Completed Inspections - 11
Date Description Inspector Results Comments
03/03/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to insulate and drywall}
03/03/2022 COT - BULD - SWG Clearance Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE GAS}
03/03/2022 RSEL - Electrical Progress Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
03/03/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, please send clearance to SWG for gas reconnection}
03/03/2022 RSBU - Building Progress Passed {Activity date: 03/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 12/23/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
South unit roof osb and trusses ok to dry in.}
04/27/2022 COT - RSEL - Temporary Service Passed {Activity date: 04/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap

Clear temp power #2}
04/27/2022 BULD - Electrical Clearance Passed {Activity date: 04/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - CODE TMPP/UNIT#2}
01/06/2023 COT - RSEL - Electrical Final Passed
01/06/2023 RSBU - Building Final Passed
01/06/2023 COT - RSPL - Gas Reconnect Passed No clearance required, gas service is operational.
01/06/2023 COT - RSPL - Plumbing Final Passed

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
INSPECTION CARD.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW