Permit: T21CM05319
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
7960 E BROADWAY BL
Address NEW:
7960 E BROADWAY BL
Apply Date:
06/28/2021
Applicant:
Description:
C of O Issued- Ground Up Construction, including Site Work of Single Story, 2 Service Bay Take 5 Oil Change with re
Permit Reviews
Permit Number - T21CM05319
Permit Status: Complete
Permit Description: C of O Issued- Ground Up Construction, including Site Work of Single Story, 2 Service Bay Take 5 Oil Change with re
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2022 | RESUBMITTAL | 03/18/2022 | COMPLETED |
| 06/28/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/06/2021 | COMPLETED |
| 11/08/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/09/2022 | APPROVED |
| 01/30/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/31/2023 | APPROVED |
Conditions
Permit Number - T21CM05319
Permit Status: Complete
Permit Description: C of O Issued- Ground Up Construction, including Site Work of Single Story, 2 Service Bay Take 5 Oil Change with re
| Date | Description | Comments |
|---|---|---|
| 02/23/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 02/23/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 02/23/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 02/23/2022 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 02/23/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 02/23/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM05319
Permite Description: C of O Issued- Ground Up Construction, including Site Work of Single Story, 2 Service Bay Take 5 Oil Change with re
Total Outstanding Inspections - 15
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Service Upgrade | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Backwater Valve | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Roof Drains | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM05319
Permit Description: C of O Issued- Ground Up Construction, including Site Work of Single Story, 2 Service Bay Take 5 Oil Change with re
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/14/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 06/14/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved } |
|
| 06/21/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/21/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/17/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval} ; {Activity date: 06/08/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Bottoms of oil pits. } |
|
| 07/07/2022 | COT - LCBU - Framing | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 07/07/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 08/10/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 08/11/2022 | COT - LCPL - Sewer | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 09/06/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/02/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Canceled per on site conversion.} | |
| 09/15/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/06/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Not Ready} ; {Activity date: 09/02/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Canceled per on site conversion.} | |
| 09/15/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/06/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Not Ready} ; {Activity date: 09/02/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Canceled per on site conversion.} | |
| 09/26/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/26/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP. Plywood on inside.} | |
| 10/04/2022 | COT - HCBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 11/29/2022 | COT - LCEL - Electrical Underground | Passed | From transformer to building. panelbox is not installed. | |
| 12/01/2022 | BULD - Electrical Clearance | Passed | ||
| 01/09/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
| 01/09/2023 | COT - LCBU - Preslab | Passed | ||
| 01/09/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/09/2023 | COT - LCEL - Electrical Final | Passed | ||
| 01/09/2023 | COT - LCEL - Electrical Progress | Passed | ||
| 01/09/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 01/09/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 01/09/2023 | COT - LCPL - Backwater Valve | Passed | ||
| 01/09/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 01/09/2023 | COT - LCBU - Building Progress | Passed | ||
| 01/25/2023 | COT - LCME - Mechanical Final | Passed | ||
| 01/25/2023 | COT - FCON - Fire - Final | Passed | ||
| 01/25/2023 | COT - LCBU - Building Final | Passed |