Permit: T21CM05217
Permit Details
Apply Date:
06/23/2021
Applicant:
Vince Voss, Stand 8
Description:
TOWER WORK: REMOVE (6) ANTENNAS, REMOVE (9) RRHS, REMOVE (1) JUNCTION BOX, REMOVE (3) COMBINERS, REMOVE (3) HYBRID CABLE (1-1/4"), REMOVE (1) HYBRID CABLE, (5/8"), REMOVE (1) POWER CABLE (7/8"), INSTALL (6) ANTENNAS, INSTALL (6) ANTENNAS, INSTALL (6) RRHS, INSTALL (2) BREAKOUT PENDANTS, INSTALL (2) HYBRID CABLES (1-1/2"), INSTALL (6) 96" PIPE MOUNTS GROUND WORK: REMOVE (2) EQUIPMENT CABINETS, REMOVE (1) POWER CABINET, REMOVE (1) BATTERY CABINET, INSTALL (1) SSC CABINET, INSTALL (1) BATTERY CABINET, INSTALL (2) JUNCTION BOXES, INSTALL (2) ASIBs, INSTALL (2) ASIKs, INSTALL (3) ABIAs, INSTALL (3) ABICs, INSTALL (6) ABILs, INSTALL (2) AMIAs, INSTALL (1) CSR IXRE V2 (Gen2)
Architects:
- NB+C Engineering Services
Contractors:
- SAC WIRELESS LLC
- TBD
Permit Reviews
Permit Number - T21CM05217
Permit Status: Final
Permit Description: TOWER WORK: REMOVE (6) ANTENNAS, REMOVE (9) RRHS, REMOVE (1) JUNCTION BOX, REMOVE (3) COMBINERS, REMOVE (3) HYBRID CABLE (1-1/4"), REMOVE (1) HYBRID CABLE, (5/8"), REMOVE (1) POWER CABLE (7/8"), INSTALL (6) ANTENNAS, INSTALL (6) ANTENNAS, INSTALL (6) RRHS, INSTALL (2) BREAKOUT PENDANTS, INSTALL (2) HYBRID CABLES (1-1/2"), INSTALL (6) 96" PIPE MOUNTS
GROUND WORK: REMOVE (2) EQUIPMENT CABINETS, REMOVE (1) POWER CABINET, REMOVE (1) BATTERY CABINET, INSTALL (1) SSC CABINET, INSTALL (1) BATTERY CABINET, INSTALL (2) JUNCTION BOXES, INSTALL (2) ASIBs, INSTALL (2) ASIKs, INSTALL (3) ABIAs, INSTALL (3) ABICs, INSTALL (6) ABILs, INSTALL (2) AMIAs, INSTALL (1) CSR IXRE V2 (Gen2)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2021 | CELL TOWER/ANTENNAS | 07/26/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM05217
Permit Description: TOWER WORK: REMOVE (6) ANTENNAS, REMOVE (9) RRHS, REMOVE (1) JUNCTION BOX, REMOVE (3) COMBINERS, REMOVE (3) HYBRID CABLE (1-1/4"), REMOVE (1) HYBRID CABLE, (5/8"), REMOVE (1) POWER CABLE (7/8"), INSTALL (6) ANTENNAS, INSTALL (6) ANTENNAS, INSTALL (6) RRHS, INSTALL (2) BREAKOUT PENDANTS, INSTALL (2) HYBRID CABLES (1-1/2"), INSTALL (6) 96" PIPE MOUNTS
GROUND WORK: REMOVE (2) EQUIPMENT CABINETS, REMOVE (1) POWER CABINET, REMOVE (1) BATTERY CABINET, INSTALL (1) SSC CABINET, INSTALL (1) BATTERY CABINET, INSTALL (2) JUNCTION BOXES, INSTALL (2) ASIBs, INSTALL (2) ASIKs, INSTALL (3) ABIAs, INSTALL (3) ABICs, INSTALL (6) ABILs, INSTALL (2) AMIAs, INSTALL (1) CSR IXRE V2 (Gen2)
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/20/2022 | FRAMING | DQUINN | Approved | Ap 1090 |
| 05/20/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 05/20/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |