Permit: T21CM05010
Permit Details
Apply Date:
06/15/2021
Applicant:
dale rush
Description:
NEW 3-STORY APARTMENT BUILDING
Permit Reviews
Permit Number - T21CM05010
Permit Status: Inspections
Permit Description: NEW 3-STORY APARTMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/15/2021 | 3RD PARTY REVIEW - COMMERCIAL | 08/04/2021 | COMPLETED |
| 08/19/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
| 06/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/21/2023 | APPROVED |
| 04/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/04/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM05010
Permit Status: Inspections
Permit Description: NEW 3-STORY APARTMENT BUILDING
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 01/17/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
| 06/15/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 07/21/2023 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - T21CM05010
Permit Status: Inspections
Permit Description: NEW 3-STORY APARTMENT BUILDING
| Date | Description | Comments |
|---|---|---|
| 01/17/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 07/21/2023 | Stair Designs must be submitted and approved prior to Final Inspection. | |
| 05/04/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T21CM05010
Permite Description: NEW 3-STORY APARTMENT BUILDING
Total Outstanding Inspections - 18
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Underground Pressure | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Kitchen Hood | N/A | Not Ready | |
| 03/22/2023 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
| 09/14/2023 | COT - LCEL - Construction Power | N/A | Partial Pass | Partial approval for Temporary Construction Power located at existing house, to be removed prior to final inspections. TMPP Clearance to TEP is required for the construction power |
| 03/22/2024 | COT - LCBU - Framing | N/A | Partial Pass | Exterior clip and nails: all areas except for exterior stairwell. Ok to stucco mesh and cover progress areas. |
| 08/07/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 8/7/23: YWL inspections need tracer wire |
| 05/01/2024 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | Duct works only. Need to install units and register system |
| 07/27/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | 7/27/23: Not ready |
| 09/20/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | 9/20/24: grounds and neutrals must be separated at sub-panels. NFPA 70 . NEC 250.142. |
| 05/02/2025 | COT - FCON - Underground Flush | N/A | Re-inspection required | Requires underground fire line permit - |
| 10/26/2022 | FCON – OH Piping & Hydro | N/A | Not Ready | |
| 12/02/2025 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | 12-2-25: loose shower flange at unit 1, paint all exterior plastics, remove nut on all vacuum breakers at hose bibs. |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
| COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections
Permit Number: T21CM05010
Permit Description: NEW 3-STORY APARTMENT BUILDING
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 08/24/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/24/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/10/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 12/27/2022 | COT - LCPL - Sewer | Passed | ||
| 12/27/2022 | COT - LCPL - Rough Soil | Passed | ||
| 02/07/2023 | COT - LCBU - Preslab | Passed | Plumbing pre-slab to be included in this inspection.. | |
| 07/27/2023 | COT - HCBU - Building Progress | Passed | ||
| 07/27/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 7/27/23: footing for stairwell passed | |
| 08/16/2023 | COT - HCPL - Yard Water Line | Passed | ||
| 04/11/2024 | COT - LCBU - Framing | Passed | ||
| 04/18/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 05/08/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
| 06/05/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 07/08/2024 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 09/26/2024 | BULD - Electrical Clearance | Passed | Ok to set meter for new service. | |
| 03/26/2025 | COT - LCEL - Outdoor Lighting | Passed | ||
| 04/28/2025 | COT - LCEL - Electrical Final | Passed | ||
| 04/28/2025 | COT - LCME - Mechanical Final | Passed |