Permit: T21CM05002
Permit Details
Apply Date:
06/15/2021
Applicant:
Dan Kishinami
Description:
New Townhome
Permit Reviews
Permit Number - T21CM05002
Permit Status: Inspections complete
Permit Description: New Townhome
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2021 | 3RD PARTY REVIEW - RESIDENTIAL | 08/04/2021 | COMPLETED |
08/19/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
04/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/01/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM05002
Permit Status: Inspections complete
Permit Description: New Townhome
Total Outstanding Activity Conditions - 7
Date | Name |
---|---|
01/17/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
01/17/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
08/04/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
08/04/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR RE-BAR |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR SOILS EXCAVATION |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR MORTAR AND GROUT |
Conditions
Permit Number - T21CM05002
Permit Status: Inspections complete
Permit Description: New Townhome
Date | Description | Comments |
---|---|---|
08/04/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: T21CM05002
Permite Description: New Townhome
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2022 | COT - LCBU - Framing | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - RSEL - Outdoor Lighting | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - LCBU - Sustainability | N/A | Canceled | Inspection Canceled |
11/04/2022 | COT - RSEL - Construction Power | N/A | Canceled | Inspection Canceled |
11/04/2022 | RSEL - Electrical Progress | N/A | Canceled | Inspection Canceled |
11/04/2022 | RSME - Mechanical Progress | N/A | Canceled | Inspection Canceled |
09/12/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | Level #1. one side: West wall |
07/27/2023 | COT - RSEL - Electrical Underground | N/A | Not Applicable | 7/27/23: Was looking to add excavation/ rebar and grounding & bonding |
09/10/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | No gas service at this site. |
08/24/2023 | COT - RSBU - Preslab | N/A | Partial Pass | Pre-slab and plumbing pre-slab. Ok,to place concrete in progress areas. Ensure slab are termite treated. |
08/12/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | This inspection is for patio CMU walls at 4’ - 8’. Ok to place grout in progress areas. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: T21CM05002
Permit Description: New Townhome
Total Completed Inspections - 16