Permit: T21CM04998
Permit Details
Apply Date:
06/15/2021
Applicant:
JR Durazo
Description:
New Townhome
Permit Reviews
Permit Number - T21CM04998
Permit Status: Issued
Permit Description: New Townhome
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2021 | 3RD PARTY REVIEW - RESIDENTIAL | 08/04/2021 | COMPLETED |
08/19/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
04/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/21/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM04998
Permit Status: Issued
Permit Description: New Townhome
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
08/04/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
08/04/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR RE-BAR |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR SOILS EXCAVATION |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR MORTAR AND GROUT |
Conditions
Permit Number - T21CM04998
Permit Status: Issued
Permit Description: New Townhome
Date | Description | Comments |
---|---|---|
08/04/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM04998
Permite Description: New Townhome
Total Outstanding Inspections - 12
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
10/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
02/15/2023 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | partial approval for UFER |
04/06/2023 | COT - RSEL - Electrical Underground | N/A | Partial Pass | UG conduit from house panel to meter pack area ok to cover |
08/15/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | Contractor cancelled. |
09/20/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | 9/20/24: grounds and neutrals must be separated at sub-panels. NFPA 70 . NEC 250.142. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM04998
Permit Description: New Townhome
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/22/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/22/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
08/10/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
02/15/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
02/15/2023 | COT - RSPL - Sewer | Passed | ||
05/04/2023 | COT - RSPL - Yard Water Line | Passed | ||
06/07/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | West side of demising/fire wall connected to 32 W 18th street | |
06/26/2023 | COT - LCBU - Framing | Passed | Interior framing and exterior sheathing; roof nailing included in this inspection | |
08/22/2023 | COT - LCPL - Plumbing Intermediate | Passed | Approved. All plumbing under pressure and secured. Including roof drains. 8/22/2023 | |
08/31/2023 | RSME - Mechanical Progress | Passed | ||
09/05/2023 | RSEL - Electrical Progress | Passed | ||
09/26/2024 | BULD - Electrical Clearance | Passed | Ok to set meter for new service. |