Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM04995
Permit Details
Apply Date:
06/15/2021
Applicant:
Dan Kishinami
Description:
New Townhome
Permit Reviews
Permit Number - T21CM04995
Permit Status: Issued
Permit Description: New Townhome
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2021 | 3RD PARTY REVIEW - RESIDENTIAL | 08/04/2021 | COMPLETED |
08/19/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
04/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/21/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM04995
Permit Status: Issued
Permit Description: New Townhome
Total Outstanding Activity Conditions - 7
Date | Name |
---|---|
01/17/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
01/17/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
08/04/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
08/04/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR RE-BAR |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR SOILS EXCAVATION |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR MORTAR AND GROUT |
Conditions
Permit Number - T21CM04995
Permit Status: Issued
Permit Description: New Townhome
Date | Description | Comments |
---|---|---|
08/04/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM04995
Permite Description: New Townhome
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
10/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
02/15/2023 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | partial approval for UFER |
08/12/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | This inspection is for CMU patio walls at 4’ - 8’. Ok to,place grout in progress areas. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM04995
Permit Description: New Townhome
Total Completed Inspections - 15
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/22/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/22/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
08/17/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to place concrete in progress areas.} | |
02/15/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
02/15/2023 | COT - RSPL - Sewer | Passed | ||
07/14/2023 | COT - LCBU - Framing | Passed | ||
07/14/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
10/05/2023 | RSME - Mechanical Progress | Passed | 10/5/23: Mechanical intermediate partial pass, all run offs per plan. Need to connect all runoffs to plenum box at A/C unit | |
10/17/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
10/17/2023 | RSEL - Electrical Progress | Passed | ||
05/14/2024 | COT - RSEL - Electrical Underground | Passed | 5/14/24: electrical underground to riser passed. Ok to backfill | |
09/10/2024 | BULD - Electrical Clearance | Passed | OK to set met and power up,system for unit #10. | |
01/17/2025 | COT - RSME - Mechanical Final | Passed | ||
01/21/2025 | COT - RSEL - Electrical Final | Passed | One kitchen countertop GFI is in operable transferring to building final | |
01/21/2025 | COT - RSPL - Plumbing Final | Passed | ||
01/22/2025 | RSBU - Building Final | Passed |