Permit: T21CM04963
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3429 E WILLARD ST
Address NEW:
3429 E WILLARD ST
Apply Date:
06/15/2021
Applicant:
Corky Poster
Description:
Renovation of existing multi-family apartment building.
Permit Reviews
Permit Number - T21CM04963
Permit Status: Complete
Permit Description: Renovation of existing multi-family apartment building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/15/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/16/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM04963
Permite Description: Renovation of existing multi-family apartment building.
Total Outstanding Inspections - 12
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 01/13/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Applicable | N/A |
| 01/13/2023 | COT - LCEL - Electrical Final | N/A | Partial Pass | Units 1-4. |
| 02/22/2023 | COT - LCME - Kitchen Hood | N/A | Not Applicable | N/A |
| 10/26/2022 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
| 10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
| 05/26/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | Not applicable. |
| 10/26/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
| 05/26/2023 | COT - LCPL - Gas Pressure Test | N/A | Not Applicable | Not applicable. No gas to building. |
| COT - FCON - Alarm - Final | N/A | Not Ready | Denied - Need Fire Alarm plans for system. | |
| 06/08/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Fire extinguishers, FACP sign, Knox box. Ok to obtain TCO level 4. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM04963
Permit Description: Renovation of existing multi-family apartment building.
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 04/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 05/04/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/04/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 05/04/2022 | COT - LCBU - Preslab | Passed | {Activity date: 05/04/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 05/25/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 06/14/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 06/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/03/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Units 4 and 8} ; {Activity date: 05/04/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Units One, two, three, five, six, seven} | |
| 06/14/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 06/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/03/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Units 4 and 8} | |
| 07/28/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 07/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved. Shower pans. } ; {Activity date: 06/21/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval require shower pan wet test all units, unit 3 not inspected} ; {Activity date: 04/21/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} |
|
| 09/16/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved. Consult on pre-clearance for TEP. } |
|
| 11/28/2022 | BULD - Electrical Clearance | Passed | Two services; Nine meters total. HP, #1, #2, #3, #4, #5, #6, #7, and #8. | |
| 01/17/2023 | COT - LCEL - Electrical Final | Passed | ||
| 01/17/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 01/17/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 01/17/2023 | COT - LCME - Mechanical Final | Passed | ||
| 04/19/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 05/26/2023 | COT - LCBU - Building Above Ceiling | Passed | Mechanical, electrical, and plumbing above ceiling is complete and functional. | |
| 05/26/2023 | COT - LCBU - Framing | Passed | ||
| 05/26/2023 | COT - LCEL - Outdoor Lighting | Passed | Exterior porch lights are installed, operational, and pointing downward. | |
| 05/26/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | Plumbing above ceiling is complete. | |
| 05/26/2023 | COT - LCPL - Plumbing Progress | Passed | Plumbing above ceiling is complete. All fixtures are installed and operational. | |
| 05/31/2023 | COT - FCON - Alarm - Final | Passed | ||
| 06/08/2023 | COT - FCON - Sprinkler - Final | Passed | Approved on 6/5/23 on permit #T22FC00290 | |
| 06/15/2023 | COT - FCON - Fire - Final | Passed | ||
| 06/20/2023 | COT - LCBU - Building Final | Passed |