Permit: T21CM04804
Permit Details
Apply Date:
06/09/2021
Applicant:
Tucson Expediting & Development
Description:
RETAIL
Architects:
- Michael Franks
Contractors:
- Epstein Construction LLC
Permit Reviews
Permit Number - T21CM04804
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/09/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/09/2021 | COMPLETED |
07/20/2021 | RESUBMITTAL | 07/30/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM04804
Permit Description: RETAIL
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/01/2021 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved, okay to cover |
09/02/2021 | PLUMBING - PRE SLAB | TGAUSP | Approved | Approved |
09/10/2021 | SHEET ROCK NAILING | DMUNIZ | Approved | Approved |
09/10/2021 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
09/10/2021 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
09/10/2021 | FRAMING | DMUNIZ | Approved | Approved |
10/01/2021 | MECHANICAL - ABOVE CEILING | TGAUSP | Approved | Approved |
10/01/2021 | PLUMBING - ABOVE CEILING | TGAUSP | Approved | Approved |
10/01/2021 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | Approved |
10/01/2021 | BUILDING ABOVE CEILING | TGAUSP | Approved | Approved |
10/08/2021 | FIRE - FINAL | wmotto | Approved | |
10/08/2021 | FIRE - ALARM FINAL | wmotto | Approved | |
10/08/2021 | FIRE SPKLR - FINAL | wmotto | Approved | |
10/15/2021 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
10/15/2021 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
10/15/2021 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |
10/15/2021 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | Approved |
10/15/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | NA |
10/15/2021 | BUILDING - PROGRESS | TGAUSP | Approved | NA |
10/15/2021 | ELECTRIC - PROGRESS | TGAUSP | Approved | NA |
10/15/2021 | PLUMBING - PROGRESS | TGAUSP | Approved | NA |
10/15/2021 | MECHANICAL - PROGRESS | TGAUSP | Approved | NA |
12/08/2021 | BUILDING - FINAL | TGAUSP | Approved |