Permit: T21CM04631
Permit Details
Apply Date:
06/03/2021
Applicant:
Architects Studio Inc.
Description:
General Manufacturing
Architects:
- Philip Veneziano
Contractors:
- COBRE
Permit Reviews
Permit Number - T21CM04631
Permit Status: C of o
Permit Description: General Manufacturing
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2022 | REVISION - - 1ST | 03/24/2022 | COMPLETED |
| 06/03/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 08/16/2021 | COMPLETED |
| 12/16/2021 | RESUBMITTAL | 12/29/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM04631
Permit Description: General Manufacturing
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/18/2022 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved, okay to proceed with pre slab |
| 02/07/2022 | PLUMBING - PRE SLAB | DMUNIZ | Approved | Approved |
| 02/07/2022 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
| 03/21/2022 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | Approved |
| 03/21/2022 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | Approved |
| 04/20/2022 | U VALUE FOR WINDOW | WGALLAGHER | Approved | Approved |
| 04/20/2022 | ROOF NAILING | WGALLAGHER | Approved | Approved |
| 04/20/2022 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Approved |
| 05/03/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved, okay to backfill progress areas |
| 05/06/2022 | STUCCO MESH | DMUNIZ | Approved | Not Applicable |
| 05/06/2022 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 05/06/2022 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 05/06/2022 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
| 05/06/2022 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 05/06/2022 | FRAMING | DMUNIZ | Approved | Approved |
| 05/12/2022 | PLUMBING - PROGRESS | TGAUSP | Approved | Approved for 4” AB soil connection to existing main at east driveway, okay to backfill progress areas |
| 05/12/2022 | SHEET ROCK NAILING | TGAUSP | Approved | Approved |
| 06/02/2022 | FIRE - ALARM FINAL | wmotto1 | Approved | |
| 06/07/2022 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 06/07/2022 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 06/07/2022 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 06/07/2022 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 06/09/2022 | FIRE SPKLR - FINAL | wmotto1 | Approved | |
| 06/15/2022 | PLUMBING - FINAL | DMUNIZ | Approved | Approved |
| 06/15/2022 | MECHANICAL - FINAL | DMUNIZ | Approved | Approved |
| 06/15/2022 | BUILDING - PROGRESS | DMUNIZ | Approved | Approved |
| 06/15/2022 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Approved |
| 06/15/2022 | MECHANICAL - PROGRESS | DMUNIZ | Approved | Approved |
| 06/17/2022 | FIRE - FINAL | cgates | Approved | |
| 06/22/2022 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Approved |
| 06/22/2022 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
| 06/22/2022 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
| 06/22/2022 | BUILDING - FINAL | DMUNIZ | Approved | Approved |