Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
05/24/2021
Applicant:
Alan Simpson
Description:
New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo

Permit Reviews

Permit Number - T21CM04378
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Start Date Submittal Complete Date Status  
05/25/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 07/07/2021 COMPLETED Review Details
07/23/2021 RESUBMITTAL 09/01/2021 COMPLETED Review Details
08/29/2022 REVISION - - 1ST 09/12/2022 COMPLETED Review Details
09/10/2021 RESUBMITTAL 10/04/2021 COMPLETED Review Details
02/21/2023 COMMERCIAL REVIEW - FULL v.2 03/16/2023 REQUIRES RESUBMIT Review Details
04/11/2023 COMMERCIAL REVIEW - FULL v.3 05/02/2023 APPROVED Review Details
11/02/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/02/2023 APPROVED Review Details
12/05/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/05/2023 APPROVED Review Details
02/16/2023 COMMERCIAL REVIEW - FULL v.1 02/21/2023 REQUIRES RESUBMIT Review Details
11/30/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/01/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T21CM04378
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Date Description Comments
12/05/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
12/05/2023 Masonry Inspection Report submittal review is required.
12/05/2023 Post-Installed Anchor Inspection Report is required.
12/05/2023 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
12/05/2023 SPECIAL INSPECTION FOR steel construction IS REQUIRED

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM04378
Permite Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
03/30/2022 COT - LCPL - Backwater Valve N/A Canceled {Activity date: 03/30/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Applicable}
11/21/2023 COT - FCON - Fire - Final N/A Partial Pass Exit signs and em lights need to be tested.
11/24/2023 COT - LCBU - Masonry Pregrout N/A Not Applicable
11/24/2023 COT - LCME - Kitchen Hood N/A Not Applicable
11/24/2023 COT - LCEL - Service Upgrade N/A Not Applicable
11/24/2023 COT - LCBU - Sustainability N/A Not Applicable
03/13/2023 COT - LCEL - Electrical Above Ceiling N/A Partial Pass partial approval for west building only
10/19/2023 BULD - Electrical Clearance N/A Partial Pass Partial, service panels for POD 4 - ECO Clearance to TEP is required for the South meters units #4113, 4213, 4313, 4114, 4214, 4314, 4115, 4215, 4315,4116, 4216, 4316, 4117, 4217, 4317, 4118, 4218, 4318 and HP-4. West meters units #4119, 4219, 4319, 4120, 4220, 4320, 4121, 4221, 4321, 4122, 4222, 4322, 4123, 4223, 4323, 4124, 4224, 4324
11/27/2023 COT - BULD - SWG Clearance N/A Not Applicable
11/20/2023 COT - LCPL - Plumbing Final N/A Partial Pass
11/24/2023 COT - LCEL - Outdoor Lighting N/A Not Ready
11/20/2023 COT - LCEL - Electrical Final N/A Partial Pass East building
11/07/2023 COT - LCBU - Building Final N/A Partial Pass Partial approval for canopy's around pod 4, electrical is not complete on lighting

Completed Inspections

Permit Status: Complete
Permit Number: T21CM04378
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Completed Inspections - 35
Date Description Inspector Results Comments
03/30/2022 COT - LCPL - Rough Soil Passed {Activity date: 03/30/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
06/09/2022 COT - FCON - Underground Pressure Passed {Activity date: 06/09/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
09/07/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 09/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/06/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 08/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, pod 4 north Building foundation ok for concrete placement.} ; {Activity date: 05/05/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready, contractor rescheduled.

}
09/07/2022 COT - LCBU - Preslab Passed {Activity date: 09/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/06/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 08/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
09/07/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 09/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
11/14/2022 COT - HCBU - Interior Shear Bracing Passed
12/01/2022 COT - LCBU - Roof Nailing Passed
03/09/2023 COT - HCBU - Exterior Clips/Sheathing Passed
03/27/2023 COT - LCME - Mechanical Intermediate Passed
03/27/2023 COT - LCBU - Framing Passed
03/27/2023 COT - LCPL - Plumbing Intermediate Passed
03/27/2023 COT - LCEL - Electrical Intermediate Passed
03/27/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
07/10/2023 COT - LCBU - Building Progress Passed
11/20/2023 COT - LCME - Mechanical Final Passed
11/21/2023 COT - FCON - Alarm - Final Passed
11/21/2023 COT - FCON - Sprinkler - Final Passed
11/22/2023 COT - FCON - Fire - Final Passed
11/24/2023 COT - LCEL - Electrical Underground Passed
11/24/2023 COT - LCME - Mechanical Progress Passed
11/24/2023 COT - LCME - Mechanical Above Ceiling Passed
11/24/2023 COT - LCBU - Building Above Ceiling Passed
11/22/2023 COT - FCON - Underground Flush Passed
11/24/2023 COT - LCPL - Plumbing Above Ceiling Passed
11/24/2023 COT - LCPL - Plumbing Roof Drains Passed
11/22/2023 FCON – OH Piping & Hydro Passed
11/24/2023 COT - LCPL - Plumbing Progress Passed
11/24/2023 COT - LCEL - Electrical Above Ceiling Passed
11/24/2023 COT - LCEL - Electrical Progress Passed
11/27/2023 COT - LCPL - Sewer Passed
11/28/2023 COT - LCPL - Plumbing Final Passed
11/28/2023 COT - LCEL - Outdoor Lighting Passed
11/28/2023 COT - LCEL - Electrical Final Passed
11/28/2023 COT - LCBU - Building Final Passed 11/28/23 recommend C/O
12/01/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
FINAL SIC POD 4-2023-11-30_V1 (1)-2023-12-05_V1.PDF DOCUMENTS VIEW
POD 4 CHLORINATION REPORT-2023-10-30_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CHECKLIST.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
DRAINAGE STATEMENT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
ONE TIME BOND EXEMPT.PDF DOCUMENTS VIEW
INSPECTION CARD.PDF DOCUMENTS VIEW
SPECS VOL 1.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT -WRONG MISSING INFO.PDF DOCUMENTS VIEW
SPECS VOL 2.PDF DOCUMENTS VIEW
STRUCTURAL CALCS VOL 1.PDF DOCUMENTS VIEW
STRUCTURAL CALCS VOL 2.PDF DOCUMENTS VIEW
STRUCTURAL CALCS VOL A.PDF DOCUMENTS VIEW
TRAFFIC IMPACT ANALYSIS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW