Permit: T21CM04378
Permit Details
Apply Date:
05/24/2021
Applicant:
Alan Simpson
Description:
New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Permit Reviews
Permit Number - T21CM04378
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/25/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/07/2021 | COMPLETED |
07/23/2021 | RESUBMITTAL | 09/01/2021 | COMPLETED |
08/29/2022 | REVISION - - 1ST | 09/12/2022 | COMPLETED |
09/10/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
02/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/16/2023 | REQUIRES RESUBMIT |
04/11/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/02/2023 | APPROVED |
11/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/02/2023 | APPROVED |
12/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/05/2023 | APPROVED |
02/16/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/21/2023 | REQUIRES RESUBMIT |
11/30/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/01/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T21CM04378
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Date | Description | Comments |
---|---|---|
12/05/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
12/05/2023 | Masonry Inspection Report submittal review is required. | |
12/05/2023 | Post-Installed Anchor Inspection Report is required. | |
12/05/2023 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
12/05/2023 | SPECIAL INSPECTION FOR steel construction IS REQUIRED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM04378
Permite Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/30/2022 | COT - LCPL - Backwater Valve | N/A | Canceled | {Activity date: 03/30/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Applicable} |
11/21/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Exit signs and em lights need to be tested. |
11/24/2023 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable | |
11/24/2023 | COT - LCME - Kitchen Hood | N/A | Not Applicable | |
11/24/2023 | COT - LCEL - Service Upgrade | N/A | Not Applicable | |
11/24/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
03/13/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | partial approval for west building only |
10/19/2023 | BULD - Electrical Clearance | N/A | Partial Pass | Partial, service panels for POD 4 - ECO Clearance to TEP is required for the South meters units #4113, 4213, 4313, 4114, 4214, 4314, 4115, 4215, 4315,4116, 4216, 4316, 4117, 4217, 4317, 4118, 4218, 4318 and HP-4. West meters units #4119, 4219, 4319, 4120, 4220, 4320, 4121, 4221, 4321, 4122, 4222, 4322, 4123, 4223, 4323, 4124, 4224, 4324 |
11/27/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
11/20/2023 | COT - LCPL - Plumbing Final | N/A | Partial Pass | |
11/24/2023 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
11/20/2023 | COT - LCEL - Electrical Final | N/A | Partial Pass | East building |
11/07/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Partial approval for canopy's around pod 4, electrical is not complete on lighting |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM04378
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/30/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 03/30/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
06/09/2022 | COT - FCON - Underground Pressure | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } | |
09/07/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/06/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 08/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, pod 4 north Building foundation ok for concrete placement.} ; {Activity date: 05/05/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready, contractor rescheduled. } |
|
09/07/2022 | COT - LCBU - Preslab | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/06/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 08/23/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 08/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
09/07/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
11/14/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
12/01/2022 | COT - LCBU - Roof Nailing | Passed | ||
03/09/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
03/27/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
03/27/2023 | COT - LCBU - Framing | Passed | ||
03/27/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/27/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
03/27/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
07/10/2023 | COT - LCBU - Building Progress | Passed | ||
11/20/2023 | COT - LCME - Mechanical Final | Passed | ||
11/21/2023 | COT - FCON - Alarm - Final | Passed | ||
11/21/2023 | COT - FCON - Sprinkler - Final | Passed | ||
11/22/2023 | COT - FCON - Fire - Final | Passed | ||
11/24/2023 | COT - LCEL - Electrical Underground | Passed | ||
11/24/2023 | COT - LCME - Mechanical Progress | Passed | ||
11/24/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
11/24/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
11/22/2023 | COT - FCON - Underground Flush | Passed | ||
11/24/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
11/24/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
11/22/2023 | FCON – OH Piping & Hydro | Passed | ||
11/24/2023 | COT - LCPL - Plumbing Progress | Passed | ||
11/24/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
11/24/2023 | COT - LCEL - Electrical Progress | Passed | ||
11/27/2023 | COT - LCPL - Sewer | Passed | ||
11/28/2023 | COT - LCPL - Plumbing Final | Passed | ||
11/28/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
11/28/2023 | COT - LCEL - Electrical Final | Passed | ||
11/28/2023 | COT - LCBU - Building Final | Passed | 11/28/23 recommend C/O | |
12/01/2023 | ENGR Engineering Final | Passed |