Permit: T21CM04377
Permit Details
Apply Date:
05/24/2021
Applicant:
Alan Simpson
Description:
New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Permit Reviews
Permit Number - T21CM04377
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/25/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/07/2021 | COMPLETED |
07/23/2021 | RESUBMITTAL | 09/01/2021 | COMPLETED |
08/29/2022 | REVISION - - 1ST | 09/12/2022 | COMPLETED |
09/10/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
04/11/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/02/2023 | APPROVED |
10/16/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/17/2023 | APPROVED |
02/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/16/2023 | REQUIRES RESUBMIT |
02/16/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/21/2023 | REQUIRES RESUBMIT |
04/24/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/18/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM04377
Permite Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Outstanding Inspections - 17
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Roof Nailing | N/A | Not Ready | |
02/21/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | north building 3 floors |
02/17/2023 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | partial approval for 5 canopy columns on west side and 7 on north side ok for concrete |
02/22/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | partial approval for west building |
08/30/2023 | BULD - Electrical Clearance | N/A | Partial Pass | 8/30/23 partial approval for north panel west side only units 3306,3206,3106, 3305, 3205, 3105, 3304, 3204 and 3104 clearance ECO 8/30/23 partial approval for east panels left and right sides 18 units, left side, 3112, 3312, 3111, 3212, 3311, 3110, 3211, 3310 and 3210. right side, 3309, 3209, 3109, 3308, 3208, 3108, 3307, 3207 and 3107. |
10/26/2022 | COT - FCON - Underground Flush | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | FCON – OH Piping & Hydro | N/A | Not Ready | |
10/25/2023 | COT - LCPL - Plumbing Final | N/A | Partial Pass | 10/25/23 Partial approval for west building only |
05/02/2023 | COT - LCBU - Building Progress | N/A | Partial Pass | interior shear wall’s building 4 |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
11/24/2023 | COT - LCME - Kitchen Hood | N/A | Not Applicable | |
11/29/2023 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable | |
02/21/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | north building 3 floors seal penetration in chase |
11/24/2023 | COT - LCBU - Sustainability | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM04377
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/30/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 03/30/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
06/09/2022 | COT - FCON - Underground Pressure | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } | |
11/14/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
12/21/2022 | COT - LCBU - Roof Nailing | Passed | ||
02/28/2023 | COT - LCPL - Plumbing Intermediate | Passed | all guest rooms in pod 3 | |
03/27/2023 | COT - HCBU - Framing | Passed | ||
05/15/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | for remainder of carport columns south side 13 each | |
07/28/2023 | COT - LCEL - Electrical Intermediate | Passed | Approved sub-panels/electrical intermediates for all units in Pod 3 | |
09/26/2023 | BULD - Electrical Clearance | Passed | 8/22/23 - Partial approval for Building #3, South (left panel)- 9 Units - #3116,#3117,#3118,#3216,#3217,#3218,#3316,#3317,#3318 Partial approval for Building #3, West Panels - 18 Units - #3119,#3120,#3121,#3122,#3123,#3124,3219,#3220,#3221,#3222,#3223,#3224,#3319,#3320,#3321,#3322,#3323,#3324 ** ECO Clearance to TEP is required for Building #3 (9 units of the South panel and 18 units of the West panel) 8/30/23 partial approval for north panel west side only units 3306,3206,3106, 3305, 3205, 3105, 3304, 3204 and 3104 clearance ECO 9/26/23: north panel (right side) units 3301,3302,3303,3101,3102,3103,3201,3202,3203 panel H3A,south panel (right side) units 3113,3114,3115,3213,3214,3215,3313,3314,3315 Panel H3B |
|
10/26/2023 | COT - FCON - Underground Flush | Passed | ||
10/26/2023 | COT - FCON - Alarm - Final | Passed | ||
10/26/2023 | COT - FCON - Sprinkler - Final | Passed | ||
10/26/2023 | FCON – OH Piping & Hydro | Passed | ||
10/31/2023 | COT - LCPL - Plumbing Final | Passed | ||
11/03/2023 | COT - LCME - Mechanical Final | Passed | please level units per manufacturer instructions | |
11/03/2023 | COT - LCEL - Electrical Final | Passed | ||
11/24/2023 | COT - LCPL - Yard Water Line | Passed | ||
11/24/2023 | COT - LCPL - Plumbing Progress | Passed | ||
11/24/2023 | COT - LCBU - Preslab | Passed | ||
11/24/2023 | COT - LCEL - Electrical Underground | Passed | ||
11/24/2023 | COT - LCBU - Building Progress | Passed | ||
11/24/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
11/22/2023 | COT - FCON - Fire - Final | Passed | ||
11/24/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
11/24/2023 | COT - LCEL - Electrical Progress | Passed | ||
11/29/2023 | COT - LCPL - Sewer | Passed | ||
11/24/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
11/29/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
11/24/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
11/24/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
11/24/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
11/24/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
11/24/2023 | COT - LCPL - Backwater Valve | Passed | ||
11/24/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
11/24/2023 | COT - LCME - Mechanical Progress | Passed | ||
11/30/2023 | COT - LCBU - Building Final | Passed | Ok for C OF O |