Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
05/17/2021
Applicant:
Description:
SFR LENNVC453 T20-M0036

Outstanding Activity Conditions

Permit Number - T21CM04222
Permit Status: Expired
Permit Description: SFR LENNVC453 T20-M0036
Total Outstanding Activity Conditions - 2
Date Name
05/17/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
05/17/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T21CM04222
Permit Description: SFR LENNVC453 T20-M0036
Total Completed Inspections - 23
Date Description Inspector Results Comments
07/09/2021 COT - RSPL - Yard Water Line Passed {Activity date: 07/09/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
07/09/2021 COT - RSPL - Sewer Passed {Activity date: 07/09/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
07/09/2021 COT - RSPL - Rough Soil Passed {Activity date: 07/09/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved}
07/23/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 07/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
07/23/2021 COT - RSBU - Preslab Passed {Activity date: 07/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
07/23/2021 COT - RSEL - Electrical Underground Passed {Activity date: 07/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
07/23/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 07/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
08/30/2021 COT - RSBU - Roof Nailing Passed {Activity date: 08/30/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/26/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - NR, cancelled by contractor} ; {Activity date: 08/23/2021; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - corrections required

Note: secure 18” GLB to 21”GLB 1st floor
}
08/30/2021 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 08/30/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/26/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - NR, cancelled by contractor} ; {Activity date: 08/23/2021; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - corrections required

Note: secure 18” GLB to 21”GLB 1st floor
}
12/16/2021 COT - LCBU - Framing Passed {Activity date: 12/16/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
12/16/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 12/16/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
12/16/2021 RSME - Mechanical Progress Passed {Activity date: 12/16/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
12/16/2021 COT - RSPL - Gas Pressure Test Passed {Activity date: 12/16/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
12/27/2021 COT - HCBU - Interior Shear Bracing Passed {Activity date: 12/27/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
01/18/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 01/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO}
01/18/2022 COT - RSEL - Construction Power Passed {Activity date: 01/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP
TEP ECO

}
03/09/2022 COT - BULD - SWG Clearance Passed {Activity date: 03/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS}
03/24/2022 COT - RSME - Mechanical Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/24/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/24/2022 COT - RSPL - Plumbing Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/09/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
SWG clearance required.}
03/24/2022 COT - RSEL - Electrical Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/29/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 03/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 12/16/2021; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO
1. Support gas line at washer box
2. Remove drywall screws from 4-gang box and support with a slide bar
3. Remove screw from vent and replace that section.}
03/29/2022 RSBU - Building Final Passed {Activity date: 03/29/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 03/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/24/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO
1. Stair handrail required to be between 34 & 38 inches off stair nosing
2. Remove all extra & broken tiles off roof}