Permit: T21CM04163
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
6257 S DEER PARK LN
Address NEW:
6257 S DEER PARK LN
Apply Date:
05/14/2021
Applicant:
Russ Salmon
Description:
SFR LENNVC353 T20-M0033
Outstanding Activity Conditions
Permit Number - T21CM04163
Permit Status: Expired
Permit Description: SFR LENNVC353 T20-M0033
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 05/14/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 05/14/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Conditions
Permit Number - T21CM04163
Permit Status: Expired
Permit Description: SFR LENNVC353 T20-M0033
| Date | Description | Comments |
|---|---|---|
| 05/14/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T21CM04163
Permite Description: SFR LENNVC353 T20-M0033
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM04163
Permit Description: SFR LENNVC353 T20-M0033
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 07/02/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
| 07/02/2021 | COT - RSPL - Sewer | Passed | {Activity date: 07/02/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
| 07/02/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/02/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
| 07/22/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 07/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 07/22/2021 | COT - RSBU - Preslab | Passed | {Activity date: 07/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 07/22/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 07/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 07/22/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 08/23/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/23/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved } |
|
| 08/23/2021 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 08/23/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved } |
|
| 12/06/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 12/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 12/06/2021 | COT - LCBU - Framing | Passed | {Activity date: 12/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 12/06/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 12/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 12/06/2021 | RSME - Mechanical Progress | Passed | {Activity date: 12/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 12/06/2021 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 12/06/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
| 12/14/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
| 02/16/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO} | |
| 02/16/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 02/16/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved clear TEP ECO} | |
| 03/07/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 03/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
| 03/23/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} | |
| 03/23/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} | |
| 03/23/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} ; {Activity date: 03/07/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA SWG clearance required} |
|
| 03/23/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} |