Permit: T21CM04148
Permit Details
Apply Date:
05/14/2021
Applicant:
LENNAR ARIZONA CONSTRUCTION INC **APA**
Description:
SFR LENNVC354 T20-M0030
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC **APA**
Outstanding Activity Conditions
Permit Number - T21CM04148
Permit Status: Final
Permit Description: SFR LENNVC354 T20-M0030
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/14/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T21CM04148
Permit Description: SFR LENNVC354 T20-M0030
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2021 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved |
| 07/13/2021 | PLUMBING - YARD WTR LINE/TEST | WGALLAGHER | Approved | Approved |
| 07/13/2021 | PLUMBING - SEWER HCS CONNECT | WGALLAGHER | Approved | Approved |
| 08/02/2021 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | No response from contact information |
| 08/02/2021 | BUILDING PRE-SLAB | WGALLAGHER | Approved | No response from contact information |
| 08/02/2021 | ELECTRIC - UFER | WGALLAGHER | Approved | No response from contact information |
| 08/02/2021 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | No response from contact information |
| 08/24/2021 | EXT METAL CLIPS/EXT SHEATHING | TGASUP | Approved | Approved |
| 08/24/2021 | ROOF NAILING | TGASUP | Approved | Approved |
| 12/07/2021 | TEP CLEARANCE - PM | TLUNDBERG | Approved | CODE ECO |
| 12/07/2021 | ELECTRIC - CONSTRUCTION POWER | TLUNDBERG | Approved | AP TEP ECO Cancel all other inspections per John Sutton. |
| 12/08/2021 | ELECTRIC - INTERMEDIATE | TLUNDBERG | Approved | AP |
| 12/08/2021 | FRAMING | TLUNDBERG | Approved | AP |
| 12/08/2021 | RESIDENTIAL INTERMEDIATE | TLUNDBERG | Approved | AP |
| 12/08/2021 | PLUMBING - GAS PRESSURE TEST | TLUNDBERG | Approved | AP |
| 12/08/2021 | MECHANICAL - INTERMEDIATE | TLUNDBERG | Approved | AP |
| 12/08/2021 | PLUMBING - INTERMEDIATE | TLUNDBERG | Approved | AP |
| 12/16/2021 | SHEET ROCK NAILING | TLUNDBERG | Approved | AP |
| 03/24/2022 | GAS CLEARANCE | TLUNDBERG | Approved | CODE |
| 04/04/2022 | ELECTRIC - FINAL | TLUNDBERG | Approved | AP |
| 04/04/2022 | OUTDOOR LIGHTING FINAL | TLUNDBERG | Approved | AP |
| 04/04/2022 | PLUMBING - FINAL | TLUNDBERG | Approved | AP |
| 04/04/2022 | MECHANICAL - FINAL | TLUNDBERG | Approved | AP |
| 05/13/2022 | BUILDING - FINAL | TLUNDBERG | Approved |